NEC 220.41 · 220.42 · 220.45 · 2023 NEC
Unit load by occupancy, how the demand factors step down, where the 2023 NEC moved everything, and worked examples for a house and an office — with a free link to the official tables.
Need the actual tables? Look up Tables 220.42(A) and 220.45 in the free NFPA viewer →
| What it covers | 2020 NEC | 2023 NEC |
|---|---|---|
| Dwelling-unit minimum load per square foot | Table 220.12 (dwelling row) and 220.14(J) | 220.41 |
| Unit lighting load for non-dwelling occupancies | 220.12 / Table 220.12 | 220.42 / Table 220.42(A) |
| Lighting load demand factors | 220.42 / Table 220.42 | 220.45 / Table 220.45 |
| Non-dwelling receptacle demand | 220.44 | 220.47 |
| Floor-area rule (what square footage counts) | Garages excluded | Garages no longer excluded — only open porches and unfinished areas not adaptable for future use |
Method is essentially unchanged — mostly a reorganization of Article 220. Older plan-review comments and textbooks will still cite the 2020 numbers. Our own summary of the 2023 NEC, not the code text. Look up Tables 220.42(A) and 220.45 in the free NFPA viewer (nfpa.org/freeaccess) and verify against the NEC edition adopted by your AHJ. Not engineering advice — service sizing is the designer of record’s call.
| Step | What you do | Watch out for |
|---|---|---|
| 1 | Measure the floor area from outside dimensions | Leave out open porches and unfinished areas not adaptable for future use. The 2023 NEC dropped the garage exclusion — garages now count (220.5(C)) |
| 2 | Pick the occupancy and read the VA per square foot (220.41 for dwellings, Table 220.42(A) otherwise) | Use the occupancy that matches how the space is actually used, not the zoning label |
| 3 | Multiply area × unit load | This is a minimum — if the actual connected lighting is higher, use the higher number |
| 4 | Dwellings: add the small-appliance and laundry circuits (220.52) to the lighting total | They go in before the demand factors, not after |
| 5 | Apply the Table 220.45 demand factors for the occupancy | Many non-dwelling occupancies (offices, stores) get no lighting demand reduction |
| 6 | Carry the result to the service or feeder calc; apply 125% to continuous load where 215.2 / 230.42 require it | Commercial lighting is typically continuous (3 hours or more) |
Our own summary of the 2023 NEC, not the code text. Look up Tables 220.42(A) and 220.45 in the free NFPA viewer (nfpa.org/freeaccess) and verify against the NEC edition adopted by your AHJ. Not engineering advice — service sizing is the designer of record’s call.
| Input / step | Value | Source |
|---|---|---|
| Floor area (incl. garage under 2023 rules) | 2,000 sq ft | Plans, outside dimensions — 220.5(C) |
| General lighting & receptacles | 2,000 × 3 VA = 6,000 VA | 220.41 |
| Two small-appliance circuits + one laundry circuit | 4,500 VA | 220.52 |
| Total before demand | 10,500 VA | Sum |
| First 3,000 VA at 100% | 3,000 VA | Table 220.45 |
| Remaining 7,500 VA at 35% | 2,625 VA | Table 220.45 |
| Net general lighting load | 5,625 VA | Carry to the Part III (standard method) service calc |
Worked example values only. Larger dwellings reach a further demand step — look up the full table in the free NFPA viewer.
| Input / step | Value | Source |
|---|---|---|
| Floor area | 5,000 sq ft | Plans |
| Unit load, office | 1.3 VA per sq ft | Table 220.42(A) |
| Lighting load | 6,500 VA | 5,000 × 1.3 |
| Demand factor | None for offices — 100% | Table 220.45 |
| Continuous-load sizing | 6,500 × 125% = 8,125 VA | 215.2 / 230.42 |
| Plus receptacles (60 × 180 VA = 10,800 VA) | First 10 kVA at 100%, rest at 50% → 10,400 VA | 220.14(I), 220.47 |
Worked example values only. If the lighting design connects more than the unit load, use the actual connected load.
| Mistake | What to do instead |
|---|---|
| Applying dwelling demand factors to an office or store | Check the occupancy row in Table 220.45 — many commercial occupancies are taken at 100% |
| Adding small-appliance and laundry VA after the demand factor | Include them in the total that the Table 220.45 steps are applied to |
| Using the unit load when the actual lighting is higher | The table is a floor, not a ceiling |
| Forgetting 125% on continuous commercial lighting | Apply the continuous-load factor when sizing the feeder or service conductors and OCPD |
| Leaving the garage out of a 2023-code dwelling calc | Under the 2023 NEC the garage area counts toward the floor area |
| Citing 2020 section numbers on a 2023 job | Update submittals and calc sheets — the plan reviewer will flag it |
Our own summary of the 2023 NEC, not the code text. Look up Tables 220.42(A) and 220.45 in the free NFPA viewer (nfpa.org/freeaccess) and verify against the NEC edition adopted by your AHJ. Not engineering advice — service sizing is the designer of record’s call.
Paste this where you want the live chart to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/charts/nec-general-lighting-load-calculation" title="General Lighting Load (NEC 220.42/220.45) — Field PM" width="100%" height="620" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/charts/nec-general-lighting-load-calculation" target="_blank" rel="noopener">General Lighting Load (NEC 220.42/220.45)</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Look up Tables 220.42(A) and 220.45 in the free NFPA viewer. NFPA offers read-only access to current NEC editions at no cost. This page explains how the tables work; it does not reproduce them. Written to the 2023 NEC — verify against the edition your AHJ has adopted.
It starts with square feet. The general lighting load is a minimum volt-amperes-per-square-foot figure set by occupancy. For dwellings it lives in 220.41 and also covers the general-use receptacles; for everything else, Table 220.42(A) lists unit loads by occupancy type. Multiply the area by the unit load and you have the connected general lighting load — unless the actual lighting is higher, in which case the actual load governs.
Then the demand factors. Table 220.45 recognizes that not everything is on at once. Dwellings, hotels, hospitals, and warehouses step down in blocks — the first block at full value and later blocks at reduced percentages. Most other occupancies, including offices and stores, stay at 100%. In a dwelling, the small-appliance and laundry circuits are added to the lighting total before those steps are applied.
2023 renumbering. Article 220 was reorganized: the old Table 220.12 unit loads are now Table 220.42(A), the dwelling minimum is 220.41, and the demand factors that used to be Table 220.42 are now Table 220.45. If a textbook or old calc sheet says “220.42 demand factors,” it is a 2020-or-earlier reference.
After the lighting load, the calc moves on to appliances, HVAC, and motors — see the cooking appliance demand guide and, for apartment buildings, the multifamily optional method. Size the conductors with the NEC 310.16 ampacity chart, pick the OCPD from the standard breaker sizes guide, lay out circuits on the panel schedule template, and check long runs with the voltage drop calculator.
Under the 2023 NEC, 220.41 sets a minimum of 3 VA per square foot for dwelling units, which also covers the general-use receptacles. Add the small-appliance and laundry circuits from 220.52, then apply the Table 220.45 demand factors. Look up the table in the free NFPA viewer at nfpa.org/freeaccess.
The non-dwelling unit loads moved to Table 220.42(A), the dwelling minimum moved to 220.41, and the lighting demand factors that used to be Table 220.42 became Table 220.45. The method is essentially the same.
Not for general lighting — under Table 220.45, occupancies not specifically listed are taken at 100%. Office receptacle loads are handled separately under 220.47, where the portion above 10 kVA can be taken at 50%.
In commercial work it usually is, because it runs three hours or more. Feeder and service conductors and overcurrent devices are then sized at 125% of the continuous portion under 215.2, 215.3, and 230.42.
Article 220 includes a conditional allowance for using an adopted energy code’s lighting power density in some non-dwelling occupancies, with monitoring and other conditions. Check the exact wording and conditions in your adopted edition before relying on it.