Change Order Markup Calculator

Price a change order the way a GC does. Enter the sub's labor, material, equipment and lower-tier costs, the sub's OH&P, your markup, your own self-perform work, insurance and bond. Get a clean line-item breakdown, the total and the effective markup.

Sub's cost
GC
Change order total$21,840.34
Direct cost
$18,000.00
Effective markup
21.3%
Same as margin
17.6%
Change order line-item breakdown
Sub labor$8,000.00
Sub material$5,000.00
Sub equipment$1,000.00
Sub OH&P (15% of sub labor, material, equipment)$2,100.00
Sub-tier (lower-tier sub) cost$2,000.00
Sub markup on sub-tier (5%)$100.00
Sub price$18,200.00
GC markup on sub work (5% of sub price)$910.00
GC self-perform labor$1,500.00
GC self-perform material$500.00
GC OH&P on self-perform (15%)$300.00
Subtotal$21,410.00
Insurance (1% of subtotal)$214.10
Bond (1% of subtotal + insurance)$216.24
Change order total$21,840.34

Markup is a percent of cost. Margin is a percent of price. Convert between them.

๐Ÿ“‹ Embed this calculator on your site โ€” freeGet the code โ†’

Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.

<iframe src="https://www.field-pm.com/embed/free/change-order-markup-calculator" title="Change Order Markup Calculator โ€” Field PM" width="100%" height="1180" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe>
<p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/change-order-markup-calculator" target="_blank" rel="noopener">Change Order Markup Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>

Share this live with your client

The owner approves the change order, so the owner wants to see the cost build-up and the field record behind it, not just a total.

In Field PM, your change orders can be shared live with your client, item by item, from your own account.

How change order markup works

A change order price is built in layers. First the sub prices its own work: sub price = sub direct cost + sub OH&P + sub-tier cost + sub markup on sub-tier. Then the GC adds GC markup on the sub's work, its own self-performed labor and material, and GC OH&P on that self-perform work. Insurance and bond go on last.

The compounding switch controls what each percent is applied to. Compounding on: the GC markup is taken on the sub price (which already includes the sub's OH&P), insurance on the subtotal, and bond on the subtotal plus insurance. Compounding off: every percent is taken on direct cost only. Your prime contract and subcontract usually say which one applies, and they often cap the percentages.

The effective markup is everything added on top of direct cost, as a percent of direct cost. Markup is a percent of cost and margin is a percent of price, so a 25% markup is only a 20% margin. Convert any number with the markup vs margin calculator.

Field PM tracks change orders on every job, next to the daily reports, crew hours and AIA pay applications they affect.

FAQ

How do you calculate markup on a change order?+

Start with direct cost: labor, material, equipment and any lower-tier subs. The sub adds its overhead and profit (OH&P). The GC adds a markup on the sub's work and its own OH&P on any self-performed work. Insurance and bond are then added as a percent. Your contract sets which percentages are allowed and what they apply to.

What does it mean when markups compound?+

Compounding means each markup is applied to a total that already includes the markups before it. The GC's markup is taken on the sub's price including the sub's OH&P, and the bond is taken on a total that includes insurance. Non-compounding means every percent is applied only to direct cost. Many contracts spell out which method to use, so check yours.

What is the difference between markup and margin?+

Markup is profit as a percent of cost. Margin is profit as a percent of the selling price. A 25% markup is a 20% margin. This calculator shows both for the whole change order. Use the free markup vs margin calculator to convert any number.

What OH&P percentages are typical on change orders?+

It varies by contract, owner and region, so there is no single answer. Many contracts cap OH&P on change orders and set a lower markup on work done by lower-tier subs. Read the changes clause in your prime contract and subcontract before you price, and enter those numbers here.

Should bond and insurance be marked up?+

That depends on your contract. Some allow bond and insurance as a pass-through cost with no markup, others allow them inside the marked-up total. This calculator adds them at the end, after all other markups, and does not mark them up. If your contract says otherwise, adjust the numbers to match.

Stop running the numbers by hand

Field PM builds the math into the platform โ€” job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.