Free remodel downtime calculator ยท No signup
Estimate the sales a store remodel program gives up while stores are closed or running at reduced capacity, then compare a shorter construction schedule.
| Current: lost while closed (per store) | $125,000 |
|---|---|
| Current: lost at reduced capacity (per store) | $187,500 |
| Current: equal to full days of sales | 12.5 |
| Current: program total | $12,500,000 |
| Shorter: lost per store | $200,000 |
| Shorter: program total | $8,000,000 |
| Value of the shorter schedule | $4,500,000 |
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/remodel-downtime-calculator" title="Store Remodel Downtime Calculator โ Field PM" width="100%" height="960" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/remodel-downtime-calculator" target="_blank" rel="noopener">Store Remodel Downtime Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
A remodel costs more than the construction contract. While a store is closed, or open with aisles blocked and departments shut, it sells less. For a program across many stores that lost revenue can be large, which is why the construction schedule matters to the business, not just to the project team.
Lost sales while closed = average daily sales ร days closed. Lost sales at reduced capacity = average daily sales ร days reduced ร (1 โ capacity %). A store open at 75% capacity loses a quarter of a normal day's sales.
Program lost sales = lost sales per store ร stores in the program. If you enter a gross margin, the calculator also shows lost gross profit, which is closer to what the business actually gives up. The shorter-schedule column shows what a faster plan is worth.
Every number here is your input, and real sales during a remodel depend on season, traffic and how customers react, so treat it as an estimate. For the pace of the program itself, see the multi-site rollout planner and the store rollout cost calculator.
Multiply average daily sales by the days the store is fully closed. For days the store stays open with part of the floor blocked, multiply daily sales by those days and by the share of capacity lost. Add the two, then multiply by the number of stores in the program.
Lost gross profit is closer to what the business actually gives up, because the store would also have paid for the goods it did not sell. Enter a gross margin to see both. Finance teams may use other measures, so use the one your company reports.
Think about what share of a normal day's sales the store can still make: departments closed, aisles blocked, parking lost, or customers staying away from the construction. It is a judgment, so it helps to compare it with sales from remodels you have already done.
Compare the value of the shorter schedule from this calculator with what it costs to build faster: overtime, night work, extra crews or prefabrication. If the sales you keep are worth more than the extra construction cost, the faster plan pays for itself.
No. This calculator only covers sales lost to downtime. Use the store rollout cost calculator for the construction budget across the program, then look at the two together.
Field PM builds the math into the platform โ job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.
Start free trial โ