Free GMP savings calculator ยท No signup

GMP Shared Savings Calculator

On a guaranteed maximum price job, see how savings under the GMP split between owner and contractor, what the owner pays, and what happens when cost runs over the GMP.

Contract
Cost of the work

Try a cost that pushes cost + fee past the GMP

Owner pays (your case)$4,793,750
Savings under GMP
$275,000
Owner share
$206,250
Contractor share
$68,750

Your case

Your case
Cost of the work$4,500,000
Contractor fee$225,000
Cost + fee$4,725,000
Savings under GMP$275,000
Owner share of savings$206,250
Contractor share of savings$68,750
Owner pays$4,793,750
Contractor fee + share (or less overrun)$293,750

Overrun case

Overrun case
Cost of the work$4,900,000
Contractor fee$245,000
Cost + fee$5,145,000
Overrun above GMP (contractor absorbs)$145,000
Owner pays$5,000,000
Contractor fee + share (or less overrun)$100,000
๐Ÿ“‹ Embed this calculator on your site โ€” freeGet the code โ†’

Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.

<iframe src="https://www.field-pm.com/embed/free/gmp-savings-split-calculator" title="GMP Shared Savings Calculator โ€” Field PM" width="100%" height="980" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe>
<p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/gmp-savings-split-calculator" target="_blank" rel="noopener">GMP Shared Savings Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>

Share this live with your client

Under a GMP the owner's share of savings depends on what was really spent. Clear cost records during the job make the final split a short conversation.

In Field PM, your change orders and invoices can be shared live with your client, item by item, from your own account.

How a GMP savings split works

Under a guaranteed maximum price (GMP) contract the owner pays the cost of the work plus the contractor's fee, up to the GMP. Final cost = cost of the work + fee, where the fee is either a percent of cost or a fixed amount.

If final cost is under the GMP: savings = GMP โˆ’ final cost. Contractor share = savings ร— contractor split %. Owner share = the rest. The owner pays final cost + contractor share, which is still less than the GMP.

If final cost is over the GMP: the owner pays the GMP and the contractor absorbs the overrun, first out of its fee and then out of its own pocket. That is what "guaranteed" means. Approved change orders normally raise the GMP, so add them to the GMP you enter.

Contracts differ on the details: whether contingency savings are shared, whether the fee is recalculated on final cost, and whether there are split tiers. This tool uses one split and your inputs, so check the numbers against your contract. For open-book jobs without a GMP, try the cost plus fee calculator.

FAQ

What is a GMP contract?+

A guaranteed maximum price contract is a cost-plus contract with a ceiling. The owner reimburses the cost of the work plus the contractor's fee, but never more than the GMP (as adjusted by approved changes). If cost runs over, the contractor pays the difference.

How are GMP savings usually split?+

The split is negotiated and written into the contract. Some contracts give all savings to the owner, others share them by a set percentage, and some use tiers where the split changes as savings grow. Enter the contractor share your contract states.

Is the fee included in the GMP?+

Usually, yes. The GMP normally covers the cost of the work, the fee, and often contingency and general conditions. This calculator compares cost of the work plus fee against the GMP, so if your GMP is built differently, adjust the inputs to match.

What happens if the job goes over the GMP?+

The owner pays the GMP and the contractor absorbs the overrun. The overrun comes out of the contractor's fee first, and if it is bigger than the fee, out of the contractor's own money. That is why contractors track cost closely on GMP work.

Do change orders change the GMP?+

Owner-approved changes to scope normally adjust the GMP up or down. Costs the contractor could have foreseen, or its own mistakes, normally do not. Add approved change orders to the GMP before you run the numbers.

Stop running the numbers by hand

Field PM builds the math into the platform โ€” job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.

Start free trial โ†’