Free calculator · no signup

AIA G702 / G703 Pay App Calculator

Build an AIA-style Application for Payment in five minutes. Enter your SOV line items, mark % complete this period, set retainage and previous billings — get current payment due and balance to finish, calculated live.

Project Header

G703 Continuation Sheet

Line-item Schedule of Values with work-completed columns

A · ItemB · DescriptionC · Sched. ValueD · From PreviousE · This PeriodF · Stored Mat.G · Total + StoredH · %I · BalanceJ · Retainage
$25,000.00100.0%$0.00$2,500.00
$85,000.00100.0%$0.00$8,500.00
$115,000.0095.8%$5,000.00$11,500.00
$160,000.0088.9%$20,000.00$16,000.00
$65,000.0068.4%$30,000.00$6,500.00
Subtotal$505,000.00$275,000.00$135,000.00$40,000.00$450,000.0089.1%$55,000.00$45,000.00

G702 Application Summary

Calculated from your SOV inputs above

1Original Contract Sum$505,000.00
2Net Change by Change Orders$0.00
3Contract Sum to Date$505,000.00
4Total Completed & Stored to Date$450,000.00
5Retainage (10%)$45,000.00
6Total Earned Less Retainage$405,000.00
7Less Previous Certificates$0.00
8Current Payment Due$405,000.00
9Balance to Finish + Retainage$145,000.00

For project: Sample Project · Contractor: Your Company · App #: 05

How AIA G702 / G703 pay applications work

The AIA G702 Application and Certificate for Payment is the standard cover sheet for construction draw requests. The G703 Continuation Sheet is the line-by-line backup showing each Schedule of Values (SOV) item, how much has been billed previously, how much is being billed this period, materials stored, percent complete, and retainage held.

The G703 columns explained

  • A · Item No — line item number from your SOV
  • B · Description — what the line represents (e.g. "Concrete foundations")
  • C · Scheduled Value — the contracted value for that line
  • D · From Previous Application — work billed in prior pay apps
  • E · This Period — work completed since the last pay app
  • F · Materials Stored — value of materials on site but not yet installed
  • G · Total + Stored — D + E + F
  • H · % — G ÷ C (percent of scheduled value complete)
  • I · Balance to Finish — C − G
  • J · Retainage — typically G × retainage % (5-10%)

G702 summary math

Line 3: Contract Sum to Date = Original Contract Sum + Net Change by COs.
Line 4: Total Completed & Stored = sum of Column G across all line items.
Line 5: Retainage = Line 4 × retainage %.
Line 6: Total Earned Less Retainage = Line 4 − Line 5.
Line 7: Less Previous Certificates = sum of all previously approved payments.
Line 8: Current Payment Due = Line 6 − Line 7. This is the new money owed this period.
Line 9: Balance to Finish + Retainage = Line 3 − Line 6.

Why owners require AIA G702 / G703

The AIA format is the industry standard for owner-architect-contractor pay applications. Architects use it to certify percent-complete claims before owners release payment. Banks use it to verify draws against construction loans. Sureties use it to monitor bonded jobs. Even when contractors hate the format, owners almost always require it.

Want this automated?

Field PM generates AIA-style pay applications from your project data.

SOV setup, change orders, billing history, retainage tracking — all rolled up into a clean PDF in one click. No more juggling Excel templates and double-entering numbers.

Start 14-day free trial →

No credit card. Cancel anytime.