Measure how often work passes QA/QC inspection the first time. Enter inspections, first-time passes and reworks by inspection type to get first pass yield (FPY) and an estimate of what the rework costs.
| Inspection type | Inspections | Passed first time | Reworks | FPY | Remove |
|---|---|---|---|---|---|
| 86.7% | |||||
| 92.5% | |||||
| 86.7% |
| Cost per rework | $550 |
|---|---|
| Rework labor hours | 124 |
| Estimated rework cost | $17,050 |
| Rework cost per inspection | $77.50 |
| Rolled yield (if types are sequential stages) | 69.5% |
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/first-pass-yield-calculator" title="First Pass Yield Calculator — Field PM" width="100%" height="940" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/first-pass-yield-calculator" target="_blank" rel="noopener">First Pass Yield Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Share this live with your client
First pass yield tells an owner how much rework is hiding in a job. Inspection results the owner can see as they happen build trust faster than a closeout binder.
In Field PM, your QA/QC inspections can be shared live with your client, item by item, from your own account.
First pass yield (FPY) = inspections passed the first time ÷ total inspections × 100. An item that fails, gets fixed and then passes still counts as a failure for FPY. That is the point: it measures work done right the first time.
Rework cost = number of reworks × (rework hours × labor rate + material + re-inspection cost). Count every rework cycle: an item that failed twice is two reworks. The costs per rework are your averages, so the result is an estimate.
Rolled yield = FPY of stage 1 × FPY of stage 2 × ... If your inspection types are stages the same work goes through in order, rolled yield is the share of work that gets through every stage with no rework. If they are unrelated inspections, ignore it.
FPY works best tracked over time and by crew or area, where it shows which work keeps coming back. Field PM records QA/QC inspections on every job, with pass and fail results and the photos behind them.
First pass yield (FPY) is the share of inspections that pass the first time, with no rework. If 100 rough-in inspections were done and 88 passed on the first try, FPY is 88%. It is a simple measure of how often work is done right the first time.
Divide the number of inspections passed on the first attempt by the total number of inspections, then multiply by 100. Items that failed and later passed after rework count as failures for FPY.
FPY looks at one inspection stage. Rolled yield multiplies the FPY of each stage that the same work goes through in order, giving the share of work that gets through every stage with no rework at all. It is always lower than any single stage's FPY.
Estimate the average cost of one rework: labor hours to fix it times your labor cost, plus material, plus the cost of inspecting it again. Multiply by the number of rework cycles. It leaves out schedule delay and knock-on effects, so the true cost is often higher.
It depends on the type of inspection, the trade and how strict the inspector is, so there is no single target. The most useful comparison is your own FPY over time and between crews, areas or subs doing the same work.