Free cost variance calculator · No signup
Budget vs actual by line. Enter each line's budget, percent complete and cost to date. Get the cost variance in dollars and percent, a CPI-style ratio, and a flag on every line running over budget.
| Line | Budget $ | % complete | Actual $ | Variance | CPI | Remove |
|---|---|---|---|---|---|---|
| $8,000 6.7% | 1.07 | |||||
| -$14,000 -9.7% | 0.91 Over | |||||
| $7,500 6.9% | 1.07 |
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/cost-variance-calculator" title="Cost Variance Calculator — Field PM" width="100%" height="820" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/cost-variance-calculator" target="_blank" rel="noopener">Cost Variance Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Share this live with your client
On an owner's budget, a variance usually shows up first as a change order or an invoice that runs ahead of progress. Seeing them early is how an owner protects contingency.
In Field PM, your change orders and invoices can be shared live with your client, item by item, from your own account.
Comparing actual cost to the full budget only works on finished lines. A line that is 40% done and has spent 40% of its budget is on track, not under budget. So each line is first turned into earned value = budget × percent complete: what the work in place should have cost.
Cost variance ($) = earned value − actual cost. Positive means under budget, negative means over. Cost variance (%) = cost variance ÷ earned value. Cost ratio (CPI) = earned value ÷ actual cost: above 1.00 you are getting more than a dollar of work per dollar spent, below 1.00 less.
The job forecast at the bottom assumes the current cost ratio holds: forecast at completion = total budget ÷ CPI. That is a simple projection, not a promise. Set percent complete to 100 on a finished line to get a plain budget vs actual comparison.
For the full earned value picture with schedule performance too, use the earned value calculator. Field PM tracks budget vs actual by phase code from crew hours, vendor bills and expenses on the PM dashboard.
Cost variance is the difference between what the work in place should have cost and what it actually cost. In earned value terms it is earned value minus actual cost. A positive number means you are under budget for the work done so far, a negative number means you are over.
Divide the cost variance by the earned value and multiply by 100. If $50,000 of work is in place and it cost $55,000, the variance is -$5,000 and the variance percent is -10%.
Without it, a line that has just started always looks under budget, because little has been spent against a large budget. Multiplying the budget by percent complete compares cost to the work actually done. On a finished line, set percent complete to 100 and you get a plain budget vs actual.
A cost ratio (CPI) of 1.00 means you are spending exactly what the budget allowed for the work done. Above 1.00 is under budget, below 1.00 is over. How far below 1.00 is acceptable depends on your contract, your fee and your contingency, so there is no single cutoff.
The forecast divides the total budget by the current cost ratio, which assumes the rest of the job performs the way it has so far. Early in a job, with little work in place, that can swing a lot. Treat it as a signal to look closer, not a final number.
Field PM builds the math into the platform — job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.