Free contingency calculator · No signup
Set design and construction contingency as a percent of base cost, check it against a simple risk list, and track what is left after draws compared with percent complete.
| Design contingency (5%) | $100,000 |
|---|---|
| Design remaining | $60,000 |
| Construction contingency (5%) | $100,000 |
| Construction remaining | $65,000 |
| Base cost + contingency | $2,200,000 |
Contingency use (38%) is at or below percent complete (40%).
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/construction-contingency-calculator" title="Construction Contingency Calculator — Field PM" width="100%" height="1080" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/construction-contingency-calculator" target="_blank" rel="noopener">Construction Contingency Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Percent method: contingency = base cost × contingency %. Many budgets carry two pots. Design contingency covers scope that is not drawn yet and is used up as the design is finished. Construction contingency covers what goes wrong in the field: conditions, coordination, missed items. Who owns each pot depends on the contract.
Risk method: list the risks you can name, each with a cost if it happens and a probability. Expected value = cost impact × probability, and the sum is a risk-based contingency. If the percent method gives far less than the risk list, the percent is probably too low for this job.
Remaining = contingency − draws so far. A simple health check compares the share of contingency used with percent complete. If 60% of contingency is gone at 40% complete, the rest of the job has less cover than the first part needed.
There is no correct contingency percent for every job. It depends on design maturity, site, delivery method and the owner's risk tolerance, so the percentages here are yours to set. Field PM tracks change orders against the job budget, which is where most contingency draws start.
The simplest way is a percent of base cost: contingency = base cost × contingency %. A more careful way lists known risks, gives each a cost and a probability, and adds up cost × probability. Many teams use the percent for budgeting and the risk list to check that the percent is reasonable.
Design contingency covers scope that is not fully drawn yet. It shrinks as the drawings are finished. Construction contingency covers problems found in the field, such as hidden conditions, coordination gaps or missed items. The contract decides who controls each one.
There is no single right number. It depends on how complete the design is, the site, the delivery method, the type of work and how much risk the owner will carry. Use your own history and your contract. The risk list in this calculator helps test whether your percent is high enough.
Compare the share of contingency used with the job's percent complete. If you have used more contingency than the share of work done, the remaining work has less cover than the work already finished needed. That is a reason to review the risks left, not proof of a problem.
No. An allowance is money set aside for a known item that is not fully defined yet, like finishes the owner has not picked. Contingency is for things nobody has identified yet. Keep them separate so you can see what each one is really covering.