Free schedule variance calculator · No signup
Compare planned percent complete with actual percent complete on a status date. Get days ahead or behind, the schedule performance index (SPI), and two forecast finish dates.
| Planned finish | Mon, Mar 1, 2027 |
|---|---|
| Forecast if the rest goes as planned | Fri, Mar 12, 2027 |
| Forecast if the current pace continues | Wed, Mar 31, 2027 |
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/schedule-variance-calculator" title="Schedule Variance Calculator — Field PM" width="100%" height="760" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/schedule-variance-calculator" target="_blank" rel="noopener">Schedule Variance Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Share this live with your client
Days behind is the number an owner plans openings, moves and tenant dates around. It needs to come from field progress, not a hopeful update.
In Field PM, your schedule and progress by phase code can be shared live with your client, item by item, from your own account.
SPI = actual % complete ÷ planned % complete on the status date. 1.00 is on schedule, above 1.00 is ahead, below 1.00 is behind.
Days behind = days elapsed × (1 − SPI). If you planned to be 42% done after 76 days and you are 36% done, you have done 36 ÷ 42 of the planned work, so you are about 11 days of progress short. A negative number means days ahead.
Two forecasts, because nobody knows which one will happen. If the rest goes as planned: finish = planned finish + days behind. If the current pace continues: finish = start + planned duration ÷ SPI. The real answer is usually somewhere in between, depending on whether you can recover.
All days here are calendar days and the math assumes progress is spread evenly over time. Real plans are rarely straight lines, so use your scheduled planned % if you have one. To turn working days into calendar dates, use the working day converter. For cost and schedule together, try the earned value calculator.
Work out the schedule performance index (SPI = actual % complete ÷ planned % complete), then multiply the days elapsed by (1 − SPI). If you are 90% of where you planned to be after 100 days, you are about 10 days behind.
SPI is the schedule performance index: how much of the planned work is actually done. An SPI of 1.00 is on schedule, 0.90 means you have done 90% of the work planned by this date, and 1.10 means you are ahead.
One assumes the rest of the job goes exactly as planned, so you finish late by the days you are already behind. The other assumes the pace so far continues for the whole job, which stretches the full duration by 1 ÷ SPI. The truth usually lands between the two, depending on whether you recover.
From your baseline schedule or your planned S-curve on the status date. If you do not have one, the straight-line button assumes progress is spread evenly from start to finish. Real jobs usually start slow, speed up and slow down at the end, so a scheduled plan is more accurate.
Calendar days. If your contract counts working days, convert with the free working day and calendar day converter, which handles 5, 6 and 7 day workweeks and holidays.