Free schedule variance calculator · No signup

Construction Schedule Variance Calculator

Compare planned percent complete with actual percent complete on a status date. Get days ahead or behind, the schedule performance index (SPI), and two forecast finish dates.

Schedule
Progress on the status date
Schedule status11 days behind
SPI
0.86
Days elapsed
76
Planned duration (days)
181
Forecast finish
Planned finishMon, Mar 1, 2027
Forecast if the rest goes as plannedFri, Mar 12, 2027
Forecast if the current pace continuesWed, Mar 31, 2027
📋 Embed this calculator on your site — freeGet the code →

Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.

<iframe src="https://www.field-pm.com/embed/free/schedule-variance-calculator" title="Schedule Variance Calculator — Field PM" width="100%" height="760" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe>
<p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/schedule-variance-calculator" target="_blank" rel="noopener">Schedule Variance Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>

Share this live with your client

Days behind is the number an owner plans openings, moves and tenant dates around. It needs to come from field progress, not a hopeful update.

In Field PM, your schedule and progress by phase code can be shared live with your client, item by item, from your own account.

How schedule variance is calculated

SPI = actual % complete ÷ planned % complete on the status date. 1.00 is on schedule, above 1.00 is ahead, below 1.00 is behind.

Days behind = days elapsed × (1 − SPI). If you planned to be 42% done after 76 days and you are 36% done, you have done 36 ÷ 42 of the planned work, so you are about 11 days of progress short. A negative number means days ahead.

Two forecasts, because nobody knows which one will happen. If the rest goes as planned: finish = planned finish + days behind. If the current pace continues: finish = start + planned duration ÷ SPI. The real answer is usually somewhere in between, depending on whether you can recover.

All days here are calendar days and the math assumes progress is spread evenly over time. Real plans are rarely straight lines, so use your scheduled planned % if you have one. To turn working days into calendar dates, use the working day converter. For cost and schedule together, try the earned value calculator.

FAQ

How do you calculate schedule variance in days?+

Work out the schedule performance index (SPI = actual % complete ÷ planned % complete), then multiply the days elapsed by (1 − SPI). If you are 90% of where you planned to be after 100 days, you are about 10 days behind.

What does SPI mean?+

SPI is the schedule performance index: how much of the planned work is actually done. An SPI of 1.00 is on schedule, 0.90 means you have done 90% of the work planned by this date, and 1.10 means you are ahead.

Why are there two forecast finish dates?+

One assumes the rest of the job goes exactly as planned, so you finish late by the days you are already behind. The other assumes the pace so far continues for the whole job, which stretches the full duration by 1 ÷ SPI. The truth usually lands between the two, depending on whether you recover.

Where does planned percent complete come from?+

From your baseline schedule or your planned S-curve on the status date. If you do not have one, the straight-line button assumes progress is spread evenly from start to finish. Real jobs usually start slow, speed up and slow down at the end, so a scheduled plan is more accurate.

Does this use working days or calendar days?+

Calendar days. If your contract counts working days, convert with the free working day and calendar day converter, which handles 5, 6 and 7 day workweeks and holidays.

Stop running the numbers by hand

Field PM builds the math into the platform — job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.

Start free trial →

Rated by contractors on

Field PM reviews on CapterraField PM reviews on GetAppField PM reviews on Software Advice