Construction Percent Complete Calculator

Work out percent complete by cost code from earned hours, installed quantities or cost, then roll it up to one weighted number for the whole job. Up to 10 lines.

Cost code lines
Cost codeBudget hrsEarned hrs%Remove
100.0%
58.3%
10.0%
Job percent complete (weighted)52.7%
Lines counted
3
Total budget hrs
2,200
Lines over 100%
0
📋 Embed this calculator on your site — freeGet the code →

Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.

<iframe src="https://www.field-pm.com/embed/free/percent-complete-calculator" title="Percent Complete Calculator — Field PM" width="100%" height="760" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe>
<p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/percent-complete-calculator" target="_blank" rel="noopener">Percent Complete Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>

Share this live with your client

Percent complete drives what the owner pays and when the owner expects the job to finish. It is only useful if it comes from installed quantities, not a guess.

In Field PM, your progress by phase code can be shared live with your client, item by item, from your own account.

How percent complete is calculated

Line percent complete = work done ÷ budget. With the hours method that is earned hours ÷ budget hours. With the quantity method it is installed quantity ÷ budget quantity. With the cost method (often called cost to cost) it is cost to date ÷ budget cost.

Job percent complete = Σ (line weight × line %) ÷ Σ line weights. Hours and cost lines are weighted by their own budget, so a 1,200 hour code counts twice as much as a 600 hour code. Quantities come in different units (feet, each, yards), so they cannot be added together. For the quantity method you enter a weight for each line, usually its budget hours or budget dollars.

Any line over 100% is counted as 100% in the roll-up and flagged. Over 100% usually means the budget quantity was low, extra work came in without a change order, or the numbers were entered against the wrong code.

A word of caution on the cost method: if a line is over budget, cost to date runs ahead of the real progress, so cost to cost will make the job look further along than it is. Installed quantities are the most honest measure when you can get them.

This is an estimate built from the numbers you enter. Field PM calculates percent complete by phase code from the quantities foremen report each day.

FAQ

How do you calculate percent complete in construction?+

For one cost code, divide the work done by the budget: installed quantity ÷ budget quantity, earned hours ÷ budget hours, or cost to date ÷ budget cost. For the whole job, weight each cost code by its budget hours or budget dollars and take the weighted average, so big codes count more than small ones.

Which method is most accurate?+

Installed quantity is usually the most honest because it measures what is physically in place. Earned hours is the same idea expressed in hours. Cost to cost is easy because the numbers come from accounting, but it overstates progress on any line that is over budget, since spending more looks like doing more.

Why can I not just average the percentages?+

A simple average treats a 20 hour cost code the same as a 2,000 hour cost code. If the small code is done and the big one has barely started, a simple average says 50% when the job is really closer to 1%. A weighted average fixes that.

What does it mean when a line goes over 100%?+

More was installed, or more hours were earned, than the budget allowed. Common causes are a low budget quantity, added scope with no change order yet, or quantities booked to the wrong code. The calculator caps that line at 100% in the roll-up and flags it so you can look into it.

How is percent complete used for billing?+

On a progress billing such as an AIA G702/G703, each schedule of values line is billed at its percent complete. Owners and architects check that percent against what they see on site, so a percent complete built from installed quantities is much easier to get approved.

Stop running the numbers by hand

Field PM builds the math into the platform — job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.