Free earned value (CPI / SPI) calculator · No signup
Enter your budget, percent complete, actual cost, and planned schedule — instantly get CPI, SPI, EAC, and cost/schedule variance, plus a plain-English read on whether the job is over or under budget and ahead of or behind schedule.
You're running 6.3% over budget (CPI 0.94) and behind schedule (SPI 0.90). At the current cost efficiency the job finishes at about $533,333 — a $33,333 overrun versus the $500,000 budget. To still land on budget you'd need to run the remaining work at a 1.06 cost efficiency (TCPI).
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/earned-value-calculator" title="Earned Value (CPI / SPI) Calculator — Field PM" width="100%" height="820" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/earned-value-calculator" target="_blank" rel="noopener">Earned Value (CPI / SPI) Calculator</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
Earned value management (EVM) turns a project into three numbers. Planned Value (PV) is the budgeted cost of the work you scheduled to be done by today. Earned Value (EV) is the budgeted cost of the work you have actually completed — your Budget at Completion times percent complete. Actual Cost (AC) is what that completed work really cost. Comparing the three tells you, objectively, where the job stands.
From those you get the two indices contractors live by. CPI = EV ÷ AC is the value earned per dollar spent — above 1.0 is under budget, below 1.0 is over. SPI = EV ÷ PV is work done versus work planned — above 1.0 is ahead of schedule, below 1.0 is behind. Extend the cost trend and you get EAC = BAC ÷ CPI (where the job lands), ETC (what is left to spend), and VAC (the gain or overrun versus the original budget).
EVM is how owners, GCs, and lenders read a job at a glance, but its power is only as good as your cost data. Learn the method in our guide to earned value management for contractors, or let the Field PM dashboard compute CPI, SPI, and EAC automatically from field-reported hours and real committed costs.
Earned value management is a project-controls method that measures cost and schedule performance against a baseline. It compares three numbers — the budgeted value of the work you planned (PV), the budgeted value of the work you actually completed (EV), and what that completed work actually cost (AC) — to tell you objectively whether a job is over or under budget and ahead of or behind schedule, in a single set of ratios.
CPI (Cost Performance Index) is EV ÷ AC — the value earned for every dollar spent. A CPI of 1.0 is on budget, above 1.0 is under budget, below 1.0 is over budget. SPI (Schedule Performance Index) is EV ÷ PV — the work done versus the work planned by this date. An SPI of 1.0 is on schedule, above 1.0 is ahead, below 1.0 is behind.
The most common EAC formula assumes current cost efficiency continues: EAC = BAC ÷ CPI. If you are spending $1.10 for every $1.00 of value (CPI 0.91), the whole budget will overrun by that same ratio. This tool also shows ETC (Estimate to Complete = EAC − AC), the remaining spend, and VAC (BAC − EAC), the projected gain or overrun versus the original budget.
A CPI and SPI of 1.0 or higher are healthy — you are on or under budget and on or ahead of schedule. Values from about 0.95 to 1.0 are usually recoverable with attention. Below 0.90 is a serious warning: on a large job even a 0.90 CPI projects a 10%+ overrun, so it warrants a documented recovery plan.
TCPI (To-Complete Performance Index) is (BAC − EV) ÷ (BAC − AC) — the cost efficiency you must hit on all remaining work to still finish at the original budget. If TCPI is well above your current CPI (say TCPI 1.15 while you are running CPI 0.90), hitting the budget is unrealistic and you should re-baseline expectations rather than promise a number you cannot deliver.
Field PM builds the math into the platform — job costing, billing, and forecasting from real field data. 30-day free trial, no credit card.
Start free trial →