Job Costing

Earned Value Management for Contractors, Without the Jargon

Earned value management has a reputation for being heavy, bureaucratic, and reserved for federal megaprojects. Strip away the acronym soup and it is just a disciplined way to answer two questions every PM already asks: am I over budget, and am I behind schedule. Three numbers feed two ratios, and those ratios tell you the truth earlier than your gut does.

Published June 21, 2026 · 8 min read

Key takeaway

Track Planned Value, Earned Value, and Actual Cost. Then CPI = EV / AC tells you cost efficiency and SPI = EV / PV tells you schedule efficiency. Above 1.0 is good, below 1.0 is a problem.

The three numbers everything is built from

Earned value uses three measurements, all expressed in dollars so they can be compared directly. The trick is that all three are stated in budget dollars except actual cost, which keeps the comparison honest.

  • Planned Value (PV): the budgeted cost of the work you scheduled to have done by now
  • Earned Value (EV): the budgeted cost of the work you have actually completed
  • Actual Cost (AC): what you have actually spent to complete that work

The two ratios that matter

Once you have the three numbers, two simple divisions tell you almost everything.

The Cost Performance Index, CPI = EV / AC, measures how efficiently you are spending. A CPI of 1.0 means you are getting exactly a dollar of budgeted work for every dollar spent. Above 1.0 means you are under budget; below 1.0 means every dollar is buying less than a dollar of progress.

The Schedule Performance Index, SPI = EV / PV, measures how efficiently you are progressing against the plan. Above 1.0 means you are ahead of schedule in dollar terms; below 1.0 means you are behind.

  • CPI = EV / AC, where above 1.0 is under budget and below 1.0 is over budget
  • SPI = EV / PV, where above 1.0 is ahead of schedule and below 1.0 is behind
  • CPI below 1.0 and SPI below 1.0 together is the danger zone: behind and bleeding cash

A worked example

Take a 100,000 dollar concrete package planned to run ten weeks at an even 10,000 dollars per week. At the end of week 5, you planned to be halfway done, so PV is 50,000 dollars.

In reality your crew has completed 40 percent of the work, so EV is 40,000 dollars (40 percent of the 100,000 dollar budget). To get that 40 percent done you have spent 48,000 dollars, so AC is 48,000 dollars.

CPI = 40,000 / 48,000 = 0.83. You are getting 83 cents of budgeted work per dollar spent, so you are over budget. SPI = 40,000 / 50,000 = 0.80. You have earned only 80 percent of what you planned to earn by now, so you are behind schedule. Both numbers are below 1.0, which is a clear signal to act before week 5 becomes week 10.

How EVM relates to the labor Performance Factor

If you already track a labor Performance Factor, EVM will feel familiar. The Performance Factor compares earned labor hours to actual labor hours, which is the same idea as CPI applied specifically to labor instead of total cost. EVM simply widens the lens to include material, equipment, and subcontractor costs and adds the schedule dimension through SPI.

Field PM rolls budget-versus-actual, productivity, and forecasting into one PM dashboard, so the inputs for EV and AC come from the same job-cost data you are already capturing in daily reports and the time clock rather than from a separate spreadsheet.

Using the indexes to forecast

The real payoff is forecasting. If your CPI has been holding around 0.83, it is naive to assume the rest of the job will magically come in on budget. A common estimate at completion divides the total budget by the current CPI: 100,000 / 0.83 is about 120,000 dollars. That projected 20,000 dollar overrun is your early warning, and you get it at week 5 instead of at closeout.

Frequently asked questions

Do I need special software to run EVM?+

No. The math is just three numbers and two divisions. The hard part is capturing accurate actual costs and an honest percent-complete, which is where consistent daily reporting and job costing matter more than any tool.

What is a good CPI or SPI?+

Exactly 1.0 means you are on plan. Most teams aim to stay at or slightly above 1.0. Sustained readings below about 0.90 deserve a hard look, because small inefficiencies compound across the remaining work.

How is EV different from just tracking percent complete?+

Percent complete tells you how far along you are. Earned value puts a budget-dollar figure on that progress so you can compare it directly against what you planned to spend and what you actually spent.

Can SPI mislead me near the end of a job?+

Yes. As a job finishes, EV approaches PV by definition, so SPI drifts back toward 1.0 even if you were chronically late. Near completion, trust the actual schedule and the critical path over the SPI number.

Run the numbers in the field, not the spreadsheet

Field PM turns daily reports into live job costing, productivity, and billing — built for self-perform contractors. 30-day free trial · no credit card · unlimited foremen, QA/QC, safety & subs always free.

Start free trial →