Free store rollout planner · No signup
Running a store rollout or remodel program? Enter how many sites start each month and how long each one takes. Get the number of sites open at once, and the crews, contractors and owner PMs you need to keep pace.
New stores or remodels kicking off each month.
Mobilization to turnover.
Crews working a site at the same time.
GC or lead contractor capacity.
Your own construction managers.
Starting 8 sites a month at 10 weeks each, you will have about 18.5 sites open at once after week 10. Plan for 37 crews, 5 contractors and 4 owner PMs. This is an estimate that assumes an even start pace.
Paste this where you want the live calculator to appear. It works on any site that allows iframes, and includes a link back to Field PM.
<iframe src="https://www.field-pm.com/embed/free/multi-site-rollout-planner" title="Multi-Site Rollout Planner — Field PM" width="100%" height="1040" loading="lazy" style="border:1px solid #e5e7eb;border-radius:12px;max-width:560px;width:100%"></iframe> <p style="font:13px/1.5 system-ui,sans-serif;margin:8px 0;color:#6b7280"><a href="https://www.field-pm.com/free/multi-site-rollout-planner" target="_blank" rel="noopener">Multi-Site Rollout Planner</a> by <a href="https://www.field-pm.com" target="_blank" rel="noopener">Field PM</a></p>
The core of this planner is one formula: active sites = sites started per week × weeks per site. Sites per week is sites per month × 12 ÷ 52. This is Little's Law. If work starts at a steady pace and each job takes the same time, the number of jobs open at once settles at that product.
Everything else scales from active sites. Crews = active sites × crews per site. Contractors = active sites ÷ sites per contractor, rounded up. Owner PMs = active sites ÷ sites per PM, rounded up. The chart shows the ramp: open sites climb for one site duration, then level off when sites finish as fast as new ones start.
This is an estimate. Real programs start in waves, and some sites run long. Build in slack, especially on contractor count, so one slow contractor does not hold up the whole program.
Field PM lets an owner connect to each contractor's account and see their shared daily reports, crew hours, photos, safety, QA/QC, schedule, progress and invoices for each site. See how it works for general contractors and owners. A portfolio dashboard that rolls every site into one view is coming.
At a steady pace, active sites = sites started per week × weeks each site takes. Start 8 stores a month (about 1.85 a week) at 10 weeks each and you will have about 18.5 sites open at any time once the program ramps up. This is Little's Law, the same math used for any steady flow of work.
Active sites climb for one site duration, then level off. If each site takes 10 weeks, the count rises every week for the first 10 weeks. After that, a site finishes about every time a new one starts, so the number of open sites holds steady.
Divide the active sites by the number of sites one contractor can run at the same time, then round up. If 18.5 sites are active and each contractor can handle 4 at once, you need 5 contractors. Most programs add one more so a single slow contractor does not stall the schedule.
It depends on travel, site size and how much the PM relies on contractor reporting. Enter your own number. When PMs can read daily reports, photos and safety records from each site without driving to it, the number they can cover usually goes up.