Free plumbing test form · Excel

Free Plumbing Pressure Test Report Template

Hydrostatic and air test records for DWV and water piping, a gas piping pressure test, gauge calibration tracking, automatic pass/fail, and a rough-in / top-out inspection checklist.

  • DWV & water test log — water or air, psi or ft of head
  • Required pressure and duration are your inputs (IPC 312 cited)
  • Actual duration, pressure drop and PASS / FAIL calculated
  • Gauge ID + calibration date with out-of-cal flag
  • Gas piping pressure test tab (IFGC 406.4 cited)
  • Rough-in / top-out checklist with READY TO COVER flag
  • Sign-off blocks for foreman, GC and inspector

Plumbing Pressure Test Report

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

DWV & Water Test Log

System, area, medium, required pressure and duration, start/end readings, actual duration, drop, PASS/FAIL, gauge, calibration, tester and witness.

02

Gas Piping Pressure Test

Fuel gas tests with pipe material and sizes, test medium, required pressure and duration per IFGC 406.4 and spec, readings and PASS/FAIL.

03

Rough-In & Top-Out Checklist

31 pre-cover items across underground, rough-in, top-out and documentation, with Yes/No/N/A counts and a READY TO COVER flag.

04

Instructions

How to set requirements, run a clean test, handle failures and retests, and keep gauges in calibration.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What test pressure and duration should I use for a plumbing test?

Use the requirement in the code your AHJ has adopted and the project specification, whichever is more stringent. In the IPC, the tests are in Section 312 (312.2 drainage and vent water test, 312.3 drainage and vent air test, 312.5 water supply system test); fuel gas tests are in IFGC Section 406. Specs often require a higher hydro pressure or a longer hold than code. The template leaves the requirement as an input so it matches your job — verify values against the edition adopted by your AHJ.

How does the pass/fail formula work?

A test passes when the start reading is at or above the required test pressure, the system held for at least the required duration, and the pressure drop is no more than the allowable drop you entered (0 when the code or spec requires no loss). A failed test stays on the log; you record the retest on a new line and reference the original test number.

Can I air test PVC or ABS drain piping?

Check first. Many plastic pipe manufacturers and AHJs prohibit or restrict air or compressed-gas testing of PVC, CPVC and ABS because of the stored energy if a joint fails. Where it is not allowed, use a water test.

Why does the template track gauge calibration?

Inspectors and QC managers increasingly ask for the gauge ID and calibration date on test records. The sheet turns the calibration date red when it is older than your calibration interval on the test date, so an out-of-cal gauge gets caught before the inspector does.

What is the rough-in / top-out checklist for?

It is the pre-cover walk: underground, rough-in, top-out and documentation items answered Yes / No / N/A. Any "No" makes the Ready to Cover flag read NO, so the wall doesn't get closed on an open deficiency.

Prove it was tight before it was covered

A plumbing pressure test report records what was tested, at what pressure, for how long, on which gauge, and who witnessed it. It is the only proof that piping was tight once walls are closed and slabs are poured — and the first thing anyone asks for when a leak shows up later.

This free Excel template gives plumbing contractors a DWV and water test log, a gas piping pressure test, and a rough-in / top-out checklist. Required pressures and durations are inputs so the report follows the code your AHJ has adopted and your project spec. Log the inspections you call on the inspection request log.

Field PM puts test records, QA/QC checklists and inspections on the foreman's phone with photos and signatures, filed to the job automatically.

The test record is what protects you after the drywall goes up

Once a wall is closed or a slab is poured, the only proof the piping was tight is the test record. When a leak shows up six months later, the first question is "was this tested, at what pressure, for how long, and who saw it?" A green tag on the permit card doesn't answer that. A test report with the system, area, pressure, hold time, start and end readings, gauge, and witness does. The free template above makes that record fast to fill out in the field and hard to argue with later.

What's in the workbook

1. DWV & Water Test Log

A 25-row log for drain, waste and vent, storm, and domestic water tests. Each line records the system (dropdown), area / floor / riser, test medium (water or air), required test pressure and unit (psi or ft of head), required duration, start and end time, start and end reading, the gauge ID and calibration date, who tested it and who witnessed it. The sheet calculates actual duration and pressure drop and returns PASS or FAIL.

2. Gas Piping Pressure Test

The same structure for fuel gas, with a pipe material / sizes column, test medium (air, nitrogen or CO2), and units in psig or inches of water column. Header fields record gas type and system operating pressure.

3. Rough-In & Top-Out Inspection Checklist

Thirty-one field items across underground, rough-in, top-out and documentation — slope, cleanouts, change-of-direction fittings, carriers and rough-in heights, venting, shield plates, hangers, water hammer arrestors, firestopping, stack support, vent terminations and more. Counts Yes / No / N/A and shows READY TO COVER.

Setting the test requirement

This template deliberately doesn't hard-code test pressures. Requirements differ between the IPC, UPC and local amendments, and the project spec often exceeds code. For reference:

  • Drainage and vent — water test: IPC 312.2 (UPC 712)
  • Drainage and vent — air test: IPC 312.3 (UPC 712)
  • Water supply system test: IPC 312.5 (UPC 609.4)
  • Fuel gas: IFGC 406.4.1 test pressure and 406.4.2 test duration (NFPA 54 Chapter 8 where adopted)

Verify section numbers and values against the edition adopted by your AHJ, then enter them in the Required Test Pressure and Required Duration columns. Put the spec section in the header so anyone reading the report knows where the number came from.

How to run a clean test

  1. Isolate what shouldn't see the pressure. Water heaters, mixing valves, pressure-reducing valves, appliances and gas regulators are not always rated for test pressure. Isolate or remove them and note it.
  2. Fill and bleed. On a hydro, fill from the low point and bleed air at the high points. Trapped air compresses and warms, and gives you a drifting gauge.
  3. Let it stabilize, then start the clock. Cold water in a warm building (or the reverse) will move the gauge. Record the start reading once the system has settled at test pressure.
  4. Use the right gauge. Pick a gauge where the test pressure sits in the middle of the dial and the increments can show the drop you're looking for. A 0–300 psi gauge won't show a 0.5 psi drop on a 10 psig gas test.
  5. Hold for the full duration. The actual duration turns amber if the hold was shorter than required.
  6. Record the end reading and get the witness. Inspector, GC super, or QC — whoever your spec requires. Their name goes on the line.
  7. If it fails, log it. A failed test isn't a bad record — it's proof the system works. Find the leak, fix it, retest on a new line, and reference the original test number in Notes.

Gas piping tests: the extra care

Gas tests are where shortcuts hurt people. Never use oxygen as a test medium. Disconnect or isolate appliances and equipment not rated for the test pressure, and don't test through the meter or regulator. Use a gauge with increments fine enough to show a small drop. After the test passes and the system is put in service, leak-check connections at turn-on and purge per code before lighting appliances. The Notes column is the place to record isolation, purge and turn-on.

The pre-cover walk

A pressure test proves the pipe is tight. It doesn't prove the pipe is right. Before calling for cover, walk the area with the checklist tab: slope and cleanouts on the underground, carriers set to the ADA heights on the fixture schedule, every trap vented, shield plates where pipe is close to the face of studs, hangers and arrestors in, firestopping matched to the listed system, and photos taken of everything that's about to disappear. One "No" means the wall doesn't close.

When to move beyond Excel

A spreadsheet works for one foreman on one job. Across several crews, test records end up on clipboards, in photos on personal phones, and in email threads. Field PM puts inspections, QA/QC checklists, test records and daily reports on the foreman's phone, with photos and signatures, and files the PDF to the job the moment it's signed. Start a free 30-day trial — no credit card required.