Free Hydrotest Test Package Template

Test package cover sheet, hydrotest report, line list, and coating / holiday inspection in one workbook. Test pressure, hold, punch, gauge calibration, and acceptance checks built in; code values stay yours to enter.

  • Package cover: lines, P&IDs, medium, design & test pressure
  • Test pressure check: P × factor × stress ratio vs. max allowable
  • Punch A / B status + pre-test walkdown checklist
  • READY FOR TEST status + release signatures
  • Hydrotest report: gauges & cal dates, static head, pressurization log
  • Hold duration, pressure drop, leaks, acceptance, witnesses
  • Line list + coating DFT / holiday inspection log

Hydrotest Test Package

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

Test Package Cover

Package ID, system, lines and P&IDs in the boundary, test medium, design and test pressure with min/max check, hold time, Punch A/B, walkdown checklist, READY status, signatures.

02

Hydrotest Report

Gauges with calibration status, low-point static head check, fill and pressurization log, hold start/end pressure and temperature, leaks, acceptance check, witnesses.

03

Line List

Line #, size, spec/class, service, fluid category, design and operating P&T, test medium and pressure, insulation, paint, NDE %, PWHT, package #.

04

Coating / Holiday

Ambient vs. dew point check, five DFT readings per joint with average vs. spec range, holiday test voltage per spec, holidays found and repaired.

05

Instructions

Step-by-step use, with code sections cited, not embedded.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What goes in a hydrotest test package?

A cover sheet identifying the package and system, the list of lines and P&IDs inside the test boundary (usually with a colored-up P&ID and a blind list), the test medium, design and test pressures, the required hold time, the punch status, a pre-test walkdown checklist, and release signatures. After the test, the hydrotest report — gauges and calibration, the pressurization log, hold readings, leaks, and witness signatures — goes in the same package for turnover.

How is hydrostatic test pressure calculated?

Under ASME B31.3 §345.4.2 the hydrostatic test pressure is at least 1.5 × design pressure, adjusted up by the ratio of allowable stress at test temperature to allowable stress at design temperature, and limited so it does not overstress the piping or exceed the rating of any component in the boundary. Other codes (B31.1, B31.4, B31.8) and owner specs use different factors. The template does not assume one — you enter the factor and stress ratio your governing code/spec requires, and it multiplies them out and checks the specified pressure against the minimum and your maximum.

How long is a hydrotest hold?

ASME B31.3 §345.2.2(a) requires the leak-test pressure to be held at least 10 minutes, then the joints examined. Many owner specifications require 30 minutes, an hour, or a chart-recorded hold. Use whichever governs — the hold time is an input on the cover sheet and the report checks the actual duration against it.

What are Punch A and Punch B items?

Punch A items must be cleared before the test — anything affecting pressure integrity or safe testing, like missing welds or NDE, wrong gaskets or bolting, or missing supports. Punch B items (paint, insulation, tags, cosmetic) can stay open and carry to the mechanical-completion punch list. The cover sheet will not read READY FOR TEST while any Punch A item is open.

Why is there a coating / holiday tab in a hydrotest package?

On pipelines and buried or coated piping, coating inspection is part of the same turnover. The tab logs ambient conditions (steel temperature vs. dew point), up to five DFT readings per joint with the average checked against the specified range, the holiday detector voltage your coating spec calls for, and holidays found and repaired.

One workbook from walkdown to signed test record

A hydrotest test package is the record that a piping system was built, inspected, and pressure-tested to its code and spec: the lines in the boundary, the test pressure and hold, the punch status at walkdown, the gauges used, the readings, any leaks, and the signatures. Owners won't accept mechanical completion without it.

This free template gives piping, pipeline, and mechanical contractors a ready-built package: cover sheet, hydrotest report, line list, and coating / holiday inspection, with formulas that catch a test pressure below the minimum, an expired gauge, a short hold, or an open Punch A item. Pair it with the weld log template to show the NDE behind every line.

When the job has a hundred packages instead of five, Field PM tracks welds, NDE, hold points, and punch against every package so the turnover book builds itself.

How a hydrotest package actually moves through the field

Every piping job ends in the same place: dozens or hundreds of test packages that each have to get walked down, punched, tested, signed, and filed before mechanical completion. The pressure test itself takes an hour or two. Getting the package ready takes days, and most of that time goes to paperwork: which lines are in the boundary, whether the NDE is really done, whether the blinds are rated for the test pressure, and whose signatures you still need. The free workbook above covers the whole cycle: cover sheet → walkdown → hydrotest report → line list → coating / holiday inspection. Every tab is built the way a QC manager reads it.

1. Build the package around the test boundary

A test package is defined by its boundary: the set of lines and components that will be filled and pressurized together. Group lines that share a design pressure, a piping class, and a test medium, and set the boundary at valves, blinds, or equipment nozzles you can isolate and that are rated for the test. The cover sheet lists every line with size, spec, from/to, P&ID, and isometric sheet, and asks whether each line's welds and NDE are complete. A single "No" keeps the package from reading READY.

Attach a P&ID with the boundary colored in and a blind list (each temporary blind, its location, its rating, and who installed and removed it). Lost blinds are one of the most common commissioning findings. Log them when they go in.

2. Test pressure: what the formula does and doesn't do

For process piping under ASME B31.3, §345.4.2 sets the hydrostatic test pressure at not less than 1.5 × design pressure, increased by the ratio of allowable stress at test temperature to allowable stress at design temperature (St/S), and limited so no component is overstressed. Pneumatic tests (§345.5) use a lower factor with extra safety requirements. B31.1 power piping, B31.4/B31.8 pipelines, and owner specs all differ. So the template doesn't build in any of these values:

  • You enter design pressure, the test factor, and the stress ratio from your code/spec.
  • The sheet calculates the minimum test pressure = P × factor × ratio.
  • You enter the specified test pressure from the approved procedure and the maximum allowable: the lowest-rated flange, valve, blind, or piece of equipment left in the boundary.
  • The check reads OK, BELOW MINIMUM, or EXCEEDS MAX.

On the report, a static head check adds elevation: water adds roughly 0.433 psi per foot, so if the test gauge is at the high point, the low point sees test pressure plus head. On a tall rack or a vertical run that can push a low-point flange over its rating. The sheet flags it before you pump.

3. The pre-test walkdown

The checklist is the list experienced test foremen already run in their heads, written down so it gets signed:

  • Welding, PWHT, and NDE complete and accepted; isos redlined to as-built
  • Relief valves, rupture disks, control valves, and instruments removed or isolated
  • Expansion joints restrained, spring hangers pinned, temporary supports added for the water weight
  • High-point vents and low-point drains in; joints left bare for examination
  • Gauges calibrated, test-manifold relief set, water quality verified (chloride limits for stainless)
  • Area barricaded, JSA reviewed, procedure approved, owner and inspector notified

The package status reads READY FOR TEST only when Punch A is zero, every checklist line is Yes or N/A, every line's NDE is complete, and the pressure check is OK.

4. Running and recording the test

The Hydrotest Report pulls the package number, medium, test pressure, hold time, and limits from the cover sheet, so nobody retypes them wrong. Log each gauge or chart recorder with its full-scale range and calibration due date. A gauge past its due date flags EXPIRED, and the acceptance check won't pass with one in service. Record every step of the fill and pressurization with pressure and temperature: liquid-full, blocked-in piping gains and loses pressure quickly as the water warms or cools, and a temperature record is how you tell a thermal drop from a leak.

Enter hold start and end, pressures, and temperatures. The sheet calculates hold duration (including holds that run past midnight), pressure drop, and temperature change, and checks them against the cover sheet. Every leak gets a location, type, repair, and retest. The acceptance box reads CRITERIA MET only when the hold is met, the drop is within the allowable, no gauge is expired, and every leak retested OK. The inspector still examines every joint and sets the final result.

5. Line list and coating inspection

The Line List tab is a line designation table: line number, size, spec/class, service, fluid service category, from/to, P&ID, design and operating pressure and temperature, test medium and pressure, insulation, paint system, NDE %, PWHT, and test package number. The Test ÷ Design column is a quick sanity check. Filter by package number to build the next cover sheet.

The Coating / Holiday tab covers field joints and coated segments. Check ambient conditions first; most specs require steel temperature at least 5 °F above dew point, but the margin is an input. Enter up to five DFT readings per joint. The average is checked against the specified min/max and the lowest reading against the spot-reading allowance (SSPC-PA 2 allows 80% of minimum; verify against your spec). Holiday detector voltage comes from your coating spec for the coating type and thickness, so you enter it rather than the sheet calculating it. Open holidays flag amber until repaired and retested.

Code references

Section references are to ASME B31.3 and SSPC / NACE (AMPP) documents as commonly adopted. Verify against the edition named in your contract and accepted by the owner and AHJ. The workbook is a record-keeping tool, not engineering advice; the approved test procedure governs.

From test packages to a turnover system

A spreadsheet works for a handful of packages. On a unit with 150 of them, the problem isn't one package but seeing all of them at once: which are waiting on NDE, which are walked down, which are tested but not signed. Field PM's weld mapping ties welds, welders, and NDE to the isometric, and QA/QC workflows run sequenced hold points with e-signatures, so a package's status is always current. Start a free 30-day trial. No credit card required.