Free SWPPP template · Excel

Free SWPPP Inspection Report Template

Construction stormwater inspection report with a 20-item BMP checklist, automatic corrective-action due dates, discharge observations and certification — plus a corrective action log and rain log with overdue flags.

  • Permit #, qualified inspector and inspection type (7-day, 14-day + storm)
  • Rainfall since last inspection vs. your storm threshold
  • BMP checklist: condition, corrective action, due date, completed, status
  • Due dates from your permit timing — flags OVERDUE automatically
  • Discharge observations and 40 CFR 122.22 certification
  • Corrective action log and rain & inspection log

SWPPP Inspection Report

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

1

Inspection Report

Permit and inspector info, inspection type and schedule, rainfall check, 20-item BMP checklist with due dates, discharges, certification and signatures.

2

Corrective Action Log

Every condition found across the job, action type, due date, completed date, days overdue and OPEN / OVERDUE / Closed — late status.

3

Rain & Inspection Log

Daily rainfall, storm events vs. threshold, storm-inspection due dates and on-time check.

4

Instructions

How to use each tab and a summary of what the EPA CGP asks for — verify your own permit.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

How often do SWPPP inspections have to be done?

Under the EPA 2022 Construction General Permit, at least once every 7 calendar days, or once every 14 calendar days plus within 24 hours of a storm event of 0.25 inches or more. Reduced frequencies apply to stabilized, arid/semi-arid and frozen sites. Most states issue their own permit with their own schedule, so verify your permit — the workbook lets you set the schedule and storm threshold.

Who can perform a SWPPP inspection?

A qualified person — someone with the training and knowledge to assess erosion and sediment controls and site conditions. Many permits require completion of an approved inspector training course or a certification such as CPESC or a state-issued card. Record the inspector's name, title and qualifications on every report.

How fast do SWPPP corrective actions need to be completed?

The EPA CGP generally requires you to start immediately and finish by the close of the next business day for maintenance or repair, and within 7 calendar days when a new or replacement control is needed — documenting why if that is infeasible. State permits vary. The report and corrective action log calculate due dates from the timing you enter and flag anything OVERDUE.

What goes in a SWPPP inspection report?

Inspection date and inspector qualifications, the type of inspection, rainfall since the last inspection, the condition of each erosion and sediment control and pollution-prevention measure, any discharges observed and what they looked like, conditions needing corrective action, and the signed certification. This template covers each of those items; add anything your state form requires.

How long do I keep SWPPP inspection records?

The EPA CGP requires keeping inspection reports, corrective action records and the SWPPP for at least 3 years after permit coverage ends. Some states require longer. Keep the reports with the on-site SWPPP during construction so an inspector can review them.

Stormwater inspections that show the work — and the fixes

A SWPPP inspection report has to show more than a walk-through. Regulators want the inspector's qualifications, the rainfall that triggered the inspection, the condition of every control, any discharge, and proof that each problem was fixed on time. This free SWPPP inspection report template captures all of it and calculates corrective-action due dates for you.

Frequencies, storm thresholds and deadlines default to the EPA 2022 Construction General Permit and can be changed to match your state permit. Items needing work carry into a corrective action log that flags anything OVERDUE, and a rain log shows every storm event and whether its inspection was done on time.

Keep it with your weather delay log and daily field reports for a complete job record.

A SWPPP inspection report that keeps up with the site

Stormwater inspections fail in two ways: the report doesn't show what the permit asks for, or the problems it finds never get fixed on time. Regulators look at both. This free SWPPP inspection report template is built around the items the EPA 2022 Construction General Permit (CGP) asks inspectors to document, and it tracks every corrective action to a due date so nothing sits open. State permits differ — every frequency, threshold and deadline in the workbook is an input so you can match yours.

What the inspection report covers

  • Site and permit. Project, address, permit or NPDES tracking number, permit type, operators, report number.
  • Qualified inspector. Name, title and training or certification — required on every report.
  • Inspection type and schedule. Routine 7-day, routine 14-day, storm event, reduced frequency, pre-construction or final. The report calculates days since the previous inspection and the next routine inspection due date from the schedule you pick.
  • Rainfall. Rainfall since the last inspection compared with your storm threshold (0.25 in. under the EPA CGP), with a plain-English storm check.
  • BMP / control checklist. Twenty common controls — silt fence and sediment barriers, fiber rolls, on-site and off-site inlet protection, construction entrance and track-out, temporary and final stabilization, slope protection, concrete washout, stockpiles, dewatering, sediment basins, check dams, outlet protection, material storage and fueling, spill kits, waste and portable toilets, buffers, and SWPPP/site-map/posting — plus blank rows for site-specific controls.
  • Discharges. Each outfall or discharge point with the receiving water or MS4, what the discharge looked like (color, odor, sheen, turbidity, floating solids, foam) and whether sediment left the site.
  • Certification and signatures. The 40 CFR 122.22(d) certification statement with signature lines for the qualified inspector and the operator's authorized signatory.

Automatic due dates and overdue flags

Pick a condition for each control — Good, Needs maintenance, Needs repair, Failed / replace, Not installed or N/A. Anything that needs work gets a due date:

  • Maintenance or repair: inspection date + your business-day deadline (EPA CGP: close of the next business day).
  • Failed / not installed: inspection date + your calendar-day deadline for new or replacement controls (EPA CGP: 7 calendar days).

Enter the completed date when the work is done. Status reads Open, OVERDUE (past due today), Closed, or Closed — late.

Corrective action log

An inspection report is a snapshot; the corrective action log is the running record across the whole job. Each row holds the date identified, report number, BMP and location, the condition found, action type, the action taken, the calculated due date, date completed, days to complete, status, days overdue, who is responsible and whether the SWPPP or site map was updated. The status block counts open, overdue, closed-late and closed-on-time items — the numbers an inspector or owner will ask about.

Rain & inspection log

Log rainfall every day. Any day at or above your storm threshold shows a storm-inspection due date and whether it was done on time, missed, or late. On a 14-day schedule, this is the record that shows you met the storm-event requirement.

SWPPP inspection tips from the field

  1. Walk the perimeter first, downhill side. That's where sediment leaves the site and where an inspector starts.
  2. Clean silt fence before it's half full. The EPA CGP requires removing sediment before it reaches half the above-ground height of perimeter controls.
  3. Check the street, not just the site. Track-out and off-site inlets are the most visible violations.
  4. Keep the site map current. Move a stockpile or add an inlet and the SWPPP map has to show it.
  5. Close the loop in writing. A corrective action without a completion date looks like it never happened.

Related tools

From spreadsheet to phone

Field PM runs inspections as mobile checklists with photos, turns every deficiency into a tracked item with a due date, and keeps the record with the job. See safety & inspections and the form library, or start a free 30-day trial — no credit card required.

This template reflects the EPA 2022 Construction General Permit in general terms. Most states issue their own construction stormwater permit with different requirements — verify your permit. This is a field record, not legal or regulatory advice.