Free startup checklist · Excel

Free Switchgear & Transformer Startup Checklist

Pre-energization checklist for switchgear, panelboards and transformers with test records, an ordered energization sequence, a temporary power plan and a GFCI / AFCI test log. Nothing reads READY TO ENERGIZE until every item is closed.

  • 60+ checks: visual / mechanical, tests, grounding, labeling, phasing
  • Energization sequence with times and initials
  • IR, TTR, winding resistance, trip & contact resistance records
  • Pass / fail against your mfr / NETA criteria
  • Live readiness summary — READY TO ENERGIZE
  • Temporary power plan + AEGCP cord & tool log
  • GFCI / AFCI device test record

Switchgear & Transformer Startup Checklist

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

Pre-Energization Checklist

Visual / mechanical, electrical tests, grounding, labeling, phasing and energization steps with Pass / Fail / N/A, recorded values and a readiness summary.

02

Test Records

Insulation resistance, transformer turns ratio (all taps), winding resistance, breaker trip tests and contact resistance with automatic pass / fail.

03

Temporary Power Plan

Temp service, distribution and panel locations, GFCI vs. AEGCP per OSHA 1926.404(b)(1), and a cord & tool inspection log with due dates.

04

GFCI-AFCI Test Record

Device-by-device trip and reset log with pass / fail and a pass-rate summary.

05

Instructions

How to use each tab and where the acceptance criteria come from.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What should be checked before energizing new switchgear?

Receiving and visual / mechanical checks (nameplate vs. submittal, anchoring, shipping splits and lugs torqued and striped, barriers and covers installed, interior clean, interlocks working, CT secondaries not open), electrical tests (insulation resistance, trip tests, contact resistance, ground-fault protection performance test where required), grounding and bonding, labeling, and phase rotation — then a controlled energization sequence with temporary grounds and LOTO accounted for.

What tests are done on a new transformer before startup?

Typically insulation resistance winding-to-winding and winding-to-ground, turns ratio on every tap, and winding resistance, plus confirming the tap is set per design and the X0 bond is in place. Acceptance criteria come from the manufacturer, the project spec and the specified ANSI/NETA ATS edition — the template lets you enter them and compares each reading.

What is an acceptable transformer turns ratio deviation?

±0.5% of the calculated ratio is the limit most specs and testing standards use, but the manufacturer and spec govern. The Test Records tab calculates the deviation for each phase on every tap and flags anything outside the tolerance you enter.

Do I need GFCI or an assured equipment grounding conductor program for temporary power?

OSHA 29 CFR 1926.404(b)(1) requires either GFCIs on all 120-volt, single-phase, 15- and 20-ampere receptacle outlets that aren't part of the permanent wiring and are in use by employees, or a written assured equipment grounding conductor program. NEC 590.6 may require GFCI for temporary receptacles regardless, depending on the edition your AHJ enforces — check both. The Temporary Power Plan tab records which method you use and logs cord and tool tests.

How do you test AFCI breakers?

With the breaker's own TEST button. Plug-in "AFCI testers" don't reliably simulate an arc and aren't a pass/fail tool. For GFCIs, use the device TEST button first; a plug-in tester needs an equipment grounding conductor to work. The GFCI-AFCI Test Record logs trip and reset for every device.

One checklist between installed and energized

A switchgear or transformer startup checklist is the record that everything between set-in-place and energized was actually done: torque, cleanliness, barriers, insulation resistance, turns ratio, trip tests, grounding, labels and phase rotation. This free Excel template keeps all of it in one workbook, with a summary that holds energization until every item is Pass or N/A.

Acceptance criteria stay with the manufacturer, the spec and the specified ANSI/NETA ATS edition — you enter them and the sheet compares every reading. Pair it with the ground resistance test report and the arc flash label data sheet for a complete pre-energization package.

In Field PM, startup checklists run as QA/QC workflows with hold-point e-signatures, and test reports and photos file themselves into the project Job Book for turnover.

Energizing new electrical gear without surprises

Energization day is when every shortcut from the last six months shows up at once — a shipping split nobody torqued, a CT secondary left open, a green bonding screw still in a sub-panel, a temporary ground left on the bus. None of those are hard to catch. They get missed because the checks live in five different places: the manufacturer's manual, the testing agency's report, the spec, the foreman's head and the GC's schedule. This free startup checklist puts them in one workbook with a readiness summary that won't read READY TO ENERGIZE until every item is Pass or N/A.

What's in the checklist

A. Receiving, visual and mechanical

Nameplate against the approved submittal and one-line. Shipping damage, braces and blocking removed. Anchorage per the detail. Shipping-split bus splices and every field lug torqued with a calibrated wrench and torque-striped — the stripe is how the next person knows it was done. Barriers, arc chutes, covers and deadfronts in place. Interior vacuumed: metal shavings from conduit work inside switchgear are a real failure mode. Breakers rack smoothly and key interlocks work. And the one that ruins days: no open-circuit CT secondaries. A CT with an open secondary under load develops dangerous voltage and can fail violently.

B. Electrical tests

The checklist items point to the Test Records tab, which captures the data:

  • Insulation resistance for bus and feeders — all six phase combinations, test voltage, the minimum acceptable value and a pass/fail on the lowest reading. See our insulation resistance testing reference for how IR tests are interpreted.
  • Transformer turns ratio on every tap, with % deviation per phase against the tolerance you set.
  • Winding resistance with the spread between phases.
  • Breaker trip tests — test current, the manufacturer's time band and the measured trip time, plus the as-left settings, which must match the coordination study.
  • Contact / bolted-joint resistance, flagged for investigation when one phase deviates too far from the lowest.
  • Ground-fault protection performance test where NEC 230.95(C) or 215.10 requires GFP — solidly grounded wye services and feeders over 150 V to ground, 1000 A and larger — with a written record for the AHJ. Verify against the edition in force.

Acceptance criteria are inputs, not hard-coded values. The manufacturer, the project spec and the specified ANSI/NETA ATS edition govern — enter what applies to your job.

C. Grounding and bonding

The main or system bonding jumper at one point only. Neutral isolated from ground at every downstream panel — which means pulling the factory bonding screw or strap in panelboards shipped as service-rated. GEC connected and sized per design, transformer X0 bonded as a separately derived system, and the ground resistance test attached. Use our ground resistance test report for that record.

D. Labeling

Equipment nameplates, arc flash labels from the engineer's study (not generic stickers — see the arc flash label data sheet), available fault current marked at the service, source identification on panels, complete directories, emergency and multiple-source signage, series-rating marking, and conductor identification.

E. Phasing and rotation

Phase rotation checked at the line side before the main is closed. Where two sources meet — a tie breaker or an ATS — phase out across the open device: like phases should read near zero volts. Record line-to-line, line-to-neutral and neutral-to-ground voltages after energization, and bump motors before coupling.

F. The energization sequence

This section is a procedure with times, not a list to skim:

  1. Switching plan reviewed with everyone; switching order issued.
  2. Personnel notified and cleared; area barricaded.
  3. Every temporary protective ground removed — count out equals count in.
  4. Lockout/tagout removed by the people who applied it.
  5. Main and all feeders open; covers on; doors latched.
  6. Operators in PPE per the arc flash label, standing to the hinge side, operating remotely where possible.
  7. Energize the source, verify voltage and rotation, close the main, then close feeders one at a time.
  8. Record initial load, schedule an infrared scan once the gear is loaded, and notify operations.

Temporary power plan

Temp power is permanent enough to hurt someone. The Temporary Power Plan tab documents the temp service (size, voltage, meter, disconnect, grounding, inspection), every temp panel, spider box and lighting string with its location and relocation date, and your ground-fault protection method under OSHA 29 CFR 1926.404(b)(1): GFCIs on all 120-volt, single-phase, 15- and 20-ampere receptacle outlets not part of the permanent wiring, or a written assured equipment grounding conductor program. If you run an AEGCP, the cord and tool log records each test, calculates the next due date at three months, and flags anything overdue or failed. NEC 590.6 may require GFCIs for temporary receptacles regardless of an AEGCP — check the edition your AHJ enforces.

GFCI and AFCI test record

One line per device: panel, circuit, location, device type, method, tripped, reset — and PASS only if both. Test with the device button first. Plug-in GFCI testers need an equipment grounding conductor to trip anything; plug-in AFCI testers aren't a valid pass/fail tool. Any device that won't trip or reset is replaced and retested, not reset and forgotten. The summary gives a pass rate for the turnover package.