Free closeout checklist · Excel

Free Project Closeout Checklist + Warranty Log

Everything between substantial completion and final payment — punch, inspections, turnover documents, attic stock, final waivers, and retainage — tracked to 100%, with a warranty log that watches expiration dates.

  • ~50 closeout items across 5 sections
  • Punch & inspections · documentation · attic stock · financial · admin
  • Responsible party, required Y/N, due date, date received
  • Status dropdown with color coding + overdue flags
  • Live % complete summary
  • Warranty log with EDATE expiration and 90-day alerts
  • Owner / architect / GC acceptance sign-off block

Project Closeout Checklist

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

Closeout Checklist

Sectioned checklist with owners, dates, status, attic-stock quantities, and a live % complete summary.

02

Warranty Log

Every equipment and system warranty with start date, duration, EDATE expiration, days left, and status.

03

Instructions

How to run closeout with the workbook, plus tips that get retainage released faster.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What is included in a construction closeout checklist?

Final punch and inspections, the certificate of occupancy, turnover documents (as-builts, O&M manuals, warranties, test and commissioning reports, training records, keys), attic stock, and the financial close — final change order reconciliation, final lien waivers, consent of surety, final pay app, and retainage release — plus demobilization and permit closeout.

When should project closeout start?

Start the closeout checklist 60–90 days before substantial completion. O&M manuals, as-builts, warranties, and final lien waivers take weeks to collect, and they are usually what holds up retainage.

How does the % complete calculation work?

The summary counts every item marked Required = Y (excluding N/A), counts how many are Complete, and divides. It also counts overdue required items whose due date has passed and turns their due dates red.

When does the warranty period start?

Usually at substantial completion, unless the contract or manufacturer says otherwise (some equipment warranties start at start-up). The Warranty Log defaults each start date to the substantial-completion date you enter and calculates expiration with EDATE.

Closeout is how you get paid

Retainage doesn’t come back when the building is finished — it comes back when the closeout package is complete. As-builts, O&M manuals, warranties, test reports, attic stock, final lien waivers, and consent of surety all have to land before the final pay app is approved.

This free construction closeout checklist gives every item an owner, a due date, and a status, then rolls it up into a % complete you can report at every OAC meeting. The warranty log calculates each expiration date so warranty claims happen before coverage ends. Pair it with our punch list template and lien waivers.

Your contract’s closeout requirements (Division 01 and the general conditions) control — adjust the list to match.

Why closeout is where margin goes to die

Most construction projects don't lose money in the field during closeout — they lose time, and time is money. Retainage sits in the owner's account while the team chases a missing O&M manual, an unsigned lien waiver from a second-tier supplier, or an as-built the electrician never finished. Meanwhile the superintendent is on the next job and the PM is juggling three. A clean construction project closeout checklist turns closeout from a scramble into a list — with owners, due dates, and a percentage you can report every week.

What's in the free closeout checklist template

  • Closeout Checklist tab — about 50 pre-written closeout items in five sections, each with Responsible Party, Required (Y/N), Due Date, Date Received, Status (Open / In Progress / Complete / N/A), Qty / Ref, and Notes.
  • Live summary — required items, complete, in progress, open, overdue, and % complete, all formula-driven.
  • Color-coded status — green for Complete, amber for In Progress, red for Open, gray for N/A. Overdue due dates turn red automatically.
  • Warranty Log tab — equipment / system, spec section, manufacturer, installer, warranty start, duration in months, EDATE expiration, days left, contact, and a status that turns amber 90 days before expiration.
  • Instructions tab — how to run closeout with the workbook, plus practical tips.

The five parts of construction closeout

1. Punch list and final inspections

Closeout starts with the substantial completion walk and the punch list that comes out of it. Track the punch in detail with our punch list template; the closeout checklist tracks the milestones — punch issued, punch complete, architect re-walk, AHJ finals for building and MEP, fire marshal final, elevator inspection, and the certificate of occupancy or temporary certificate of occupancy (TCO). Without the CO, the owner can't legally occupy, and nothing else in closeout matters much.

2. Documentation and turnover

This is the section that usually holds up final payment. The owner needs everything required to operate and maintain the building:

  • As-built / record drawings from every trade, reflecting field changes, RFIs, and change orders
  • O&M manuals for all equipment, often in both bound and electronic form
  • Warranties — manufacturer and contractor — logged on the Warranty Log tab
  • Test reports — test & balance, fire alarm, sprinkler hydrostatic, electrical megger, backflow
  • Commissioning reports and functional performance test results
  • Owner training — sign-in sheets and recorded videos
  • Keys and access — keying schedule, cores, access cards, and codes, with a signed transmittal

Tip: put closeout documents on your submittal log at the start of the job. O&M manuals and warranty forms can be reviewed well before the building is finished.

3. Attic stock and spare parts

Specs usually require extra material — ceiling tile, flooring, paint, filters, spare sprinkler heads, lamps — turned over to the owner. Record quantities in the Qty / Ref column, photograph the stock, and get the owner to sign a transmittal. Missing attic stock is one of the easiest punch items to avoid and one of the most annoying to resolve after demob.

4. Financial closeout

The money side of closeout has a specific order:

  1. Reconcile change orders — every CO executed, pending COs resolved or withdrawn.
  2. Resolve backcharges against subcontractors and document them.
  3. Collect final lien waivers from every subcontractor and supplier — conditional with the final pay app, unconditional once payment clears. Use our free lien waiver templates.
  4. Consent of surety to final payment on bonded jobs, and the contractor's affidavit of payment of debts and claims when required.
  5. Final pay application — your schedule of values should be at 100% with retainage shown.
  6. Retainage release — owner to GC, then GC to subs.

5. Administrative closeout

Demobilize trailers, fencing, temporary power, and dumpsters; transfer utilities to the owner; close permits with the AHJ; terminate stormwater permits where applicable; complete final cleaning and site restoration; archive project records; and hold a lessons-learned meeting while the job is still fresh. Put the 11-month warranty walk on the calendar before you leave — it's much easier to get warranty work done while the one-year correction period is still open.

How to use the warranty log

Enter the substantial completion date once at the top of the Warranty Log; every row's warranty start points at it. Then enter duration in months — 12 for a typical one-year warranty, 60 for a five-year compressor warranty, 240 for a 20-year NDL roof. Expiration is calculated with EDATE, Days Left counts down from today, and Status turns amber 90 days before expiration so you can schedule warranty claims while coverage is still active. If a piece of equipment started its warranty at start-up instead of substantial completion, just overwrite that row's start date.

Common closeout mistakes

  • Starting too late. If you start collecting closeout documents at the final walk, you're already 60 days behind.
  • "The subs" as responsible party. Name the company and the person. Vague ownership means nothing moves.
  • Missing supplier waivers. Second-tier suppliers can still file liens. Get waivers from everyone who furnished material.
  • No transmittals. If you can't prove the owner received the O&Ms, keys, and attic stock, you'll be asked for them again.
  • Forgetting insurance. Completed-operations coverage matters after you leave. Keep your certificate of insurance tracker with the closeout file.

When to move closeout out of Excel

A spreadsheet works for one project. When you're closing out several jobs at once, documents land in email, the job file, and three shared drives, and nobody knows which version is final. Field PM keeps the job book, punch list, daily reports, and project documents in one place, so closeout is a matter of checking what's already filed. Start a free 30-day trial — no credit card required.