Free responsibility matrix · Excel

Free Scope Responsibility Matrix Template

Furnish, install, and connect — by party — for every item that crosses a trade line. Pre-loaded with a realistic Div 23 / Div 26 / Div 28 split and an automatic check that flags gaps and overlaps.

  • 28 pre-seeded MEP interface items — VFDs, starters, disconnects, duct smokes, fire/smoke dampers, thermostats, pads
  • 9 parties: Owner, GC, Electrical, Mechanical, Plumbing, Controls, Fire Alarm, Low Voltage, Other
  • F / I / C / F-I / I-C / F-C / F-I-C / — dropdowns
  • Automatic GAP and OVERLAP flag on every row
  • Summary: items OK, gaps, overlaps, % clean
  • Sign-off block for each trade
  • Print-ready landscape layout with repeating headers

Scope Responsibility Matrix

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

Responsibility Matrix

Items down the side, parties across the top. Pick F, I, or C in each cell; the sheet counts furnishers, installers, and connectors and flags every gap or overlap.

02

Instructions

How to build the list, what each code means, how the check works, and an OFCI / CFCI / OFOI glossary. The matrix ships with two real-world gaps and one overlap already flagged so you can see how it reads.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What is a scope responsibility matrix?

A scope responsibility matrix (also called a division of responsibility, DOR, or furnish/install/connect matrix) is a table that lists every item that crosses a trade line and states which party furnishes it, which installs it, and which makes the final connection. It is used at bid, buyout, and precon to stop items from falling between Div 23, Div 26, Div 28, and the GC.

What do F, I, and C mean?

F = Furnish: buys the item and delivers it. I = Install: sets, mounts, and supports it. C = Connect: makes the final power, control, or piping termination. Combined codes like F-I (furnish and install) or I-C (install and connect) cover the common splits — for example, a VFD furnished by the mechanical contractor and installed and wired by the electrician is Mechanical F, Electrical I-C.

How does the gap and overlap check work?

For each row the sheet counts how many parties have an F, an I, and a C. No installer or no furnisher is flagged as a GAP. Two installers or two furnishers is flagged as an OVERLAP. If you mark the item as needing a connection and nobody has a C, it is flagged "GAP – no connection". Two connectors are allowed because power and control terminations are often split between trades.

Who should own the responsibility matrix?

On most commercial jobs the GC or CM owns it and issues it with the bid packages, then updates it at buyout. On design-build and MEP-led jobs the mechanical or electrical contractor often builds it. Whoever owns it, every trade on the matrix should review and sign it before subcontracts are finalized.

Does the matrix override the specifications?

No. The matrix is a coordination tool that interprets the contract documents. If the specs conflict — for example Div 23 says "power by Div 26" and Div 26 is silent — the fix is an RFI or addendum, then update the matrix to match the answer.

One furnisher, one installer, one connector — for every item

A responsibility matrix — also called a division of responsibility or furnish/install/connect (F-I-C) matrix — spells out which party buys, sets, and terminates every item that crosses a trade line. It is the fastest way to catch the classic MEP scope gaps: fire/smoke damper power nobody carried, loose-shipped thermostats, VFDs bought by one trade and wired by another.

This free Excel template is pre-loaded with the Div 22 / 23 / 26 / 27 / 28 interface items that cause the most trouble and checks every row automatically. Gaps become RFIs; overlaps become deducts. Pair it with the bid leveling matrix to plug excluded scope when you compare sub bids.

Once the job is bought, Field PM keeps RFIs, submittals, change orders, and subcontract scope in one project record so the gaps you find stay closed.

The furnish / install / connect matrix: how MEP scope gaps get caught before they become change orders

Every experienced PM has a story that starts with "I thought you had it." The fire/smoke damper actuators that need 120V and nobody carried the circuits. The line-voltage thermostats that shipped loose in a box on the unit heater and sat in the conex until punch. The housekeeping pads that were in the concrete bid and the mechanical bid. None of these are big items. All of them show up as change orders, schedule delays, or money left on the table. A scope responsibility matrix is how you find them on paper instead of in the field.

What a responsibility matrix is (and what it isn't)

A responsibility matrix — also called a division of responsibility (DOR), an F-I-C matrix, or an MEP coordination matrix — is a one-page grid. Items go down the side, parties go across the top, and every cell says what that party does for that item: furnish, install, connect, or nothing. It's not a scope of work or a subcontract exhibit by itself. It's the cross-reference that makes sure the scopes you did write add up to 100% of the job with nothing counted twice.

The template above is pre-loaded with 28 of the most common interface items on a commercial building — the Div 23 / Div 26 / Div 28 split that causes the most trouble — plus the owner, GC, plumbing, controls, and low-voltage columns you'll need on nearly every job.

F, I, C — the three verbs that matter

CodeMeansTypical example
FFurnish — buys it, delivers it to siteMechanical furnishes the VFDs specified in Div 23
IInstall — receives, sets, mounts, supportsMechanical installs duct smoke detector housings in the duct
CConnect — final power, control, or piping terminationElectrical connects power to the rooftop unit disconnect
F-IFurnish and installPlumbing furnishes and installs the water heater
I-CInstall and connectElectrical mounts the VFD and wires line and load
F-CFurnish and connect (someone else installs)Fire alarm furnishes and wires the duct smoke detector; mechanical mounts it
F-I-CThe whole thingElectrical furnishes, installs, and wires the equipment disconnects
Explicitly not in this party's scopeUse it to show you looked and decided

The Div 23 / Div 26 / Div 28 items that cause the most trouble

These are the lines pre-seeded in the matrix, with the split you'll see on most commercial jobs. Your specs may say otherwise — the point is to read them and write the answer down.

Motor control and power

  • VFDs — commonly furnished by Div 23 (they're specified with the equipment), installed and wired line/load by Div 26, and connected for start/stop, speed reference, and BACnet by controls. Three parties, one device — it has to be on the matrix.
  • Motor starters — factory-mounted starters come with packaged equipment (Mechanical F-I, Electrical C). Loose starters and MCC buckets are usually Div 26 F-I-C. Check coil voltage and auxiliary contacts needed by controls.
  • Disconnect switches — usually Div 26, unless the equipment schedule calls for unit-mounted disconnects. Look at the mechanical schedule's "disconnect by" column if there is one. For motor full-load current and disconnect sizing references, see our motor FLC chart.
  • Line-voltage thermostats on unit heaters — shipped loose by Div 23, installed and wired by Div 26. Classic "it was in the box" item.
  • Condensate pumps — often missing from the electrical drawings entirely. The template flags this one as an example gap.

Controls / BAS

  • Control wiring — low-voltage sensors, actuators, and relays by the controls contractor (Div 23 09 xx).
  • 120V to BAS panels — typically electrical brings a dedicated circuit to a junction box; controls makes the final connection. Get panel locations early or you'll be relocating circuits.
  • Thermostats and space sensors — controls furnishes, installs, and wires the device; electrical often provides back boxes and conduit stubs. Two rows, two responsible parties.

Fire alarm and life-safety interfaces

  • Duct smoke detectors — fire alarm furnishes and wires; mechanical mounts the housing and sampling tubes in the duct. Whether one is required on a given unit depends on airflow thresholds in the mechanical code — verify against the edition adopted by your AHJ.
  • Fire/smoke dampers — the damper is mechanical. The 120V actuator power is the single most common gap on commercial jobs: Div 23 says "power by Div 26," and Div 26 shows nothing. The template seeds it as a GAP so you can see what the check looks like.
  • Flow and tamper switches, elevator recall and shunt trip, door hold-opens — each touches fire alarm plus another trade. Put every one on its own row.

Pads, supports, and owner equipment

  • Housekeeping pads — frequently carried by the concrete sub and the mechanical sub. The template shows it as an example OVERLAP. One of them gets a deduct.
  • OFCI equipment (owner-furnished, contractor-installed) — decide who receives, unloads, stores, sets, and connects, and who owns the warranty if it's damaged on site.

How the gap / overlap check works

For each row the sheet counts how many parties have an F, an I, and a C:

  • No installer or no furnisherGAP. Nobody is carrying it.
  • Two installers or two furnishersOVERLAP. Someone is getting paid twice, or you're carrying it twice in your number.
  • Connection required = Y and no CGAP – no connection. The equipment gets set and never gets wired.
  • Two connectors is allowed — power and control connections are normally split. If you want to be precise, split the row ("VFD — line/load power" and "VFD — control & BACnet").

A summary block at the top counts OK, gaps, and overlaps, and tells you when the matrix is clean. A row under the table counts how many items each party has — a quick sanity check when you hand a trade its column.

When to build it: bid, buyout, precon

  1. At bid. Estimators on both sides of the line read each other's spec sections. Every gap you find is either an RFI (see the pre-bid RFI log) or a clear qualification in your proposal.
  2. At buyout. The GC attaches the matrix to each subcontract as a scope exhibit, and uses it to level sub bids — an item one sub excluded is a plug in the bid leveling matrix.
  3. At precon. Walk the matrix line by line with every MEP and fire alarm foreman in the room. Have each party sign. Re-issue with a revision date when anything changes.

Common mistakes

  • Listing every item on the job. The matrix is for interfaces. If a single trade furnishes, installs, and connects it with no one else involved, it doesn't need a row.
  • Leaving cells blank instead of using "—". A blank cell means nobody looked. A dash means somebody decided.
  • Treating it as the contract. The matrix interprets the documents; it doesn't replace them. When the specs conflict, get an addendum or RFI answer and then update the matrix.
  • Building it once. Change orders, value engineering, and substitutions change who does what. Update it and re-issue.

From spreadsheet to project record

The matrix finds the gaps; something still has to track them to closure. Field PM keeps RFIs and change orders, submittals, and subcontract scope in one project record, so the gap you find on the matrix becomes a tracked RFI — and if it turns into a change, the cost lands on the right budget line. Start a free 30-day trial — no credit card required.