Free Excel template · EPC & turnover

Free Rules of Credit Progress Measurement Template

Measure physical progress by weighted milestones: rules of credit by discipline, earned % and earned hours for every line item, and a discipline rollup with productivity against actual hours.

  • ✓Weighted milestone steps for 6 disciplines
  • ✓Weight check: every discipline must total 100%
  • ✓Step completion 0 to 100% per line item
  • ✓Earned %, earned quantity and earned hours
  • ✓Discipline rollup with in-cell progress bars
  • ✓Productivity factor: earned ÷ actual hours

Rules of Credit Template

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

Rules of Credit

Milestones and weights for civil, steel, piping, equipment, electrical cable and instrumentation, with a description of when each step earns credit and a 100% check.

02

Progress

Line items with discipline, quantity and budget hours. Mark each step's completion and the earned %, earned quantity and earned hours calculate from the weights.

03

Discipline Rollup

Budget vs earned hours by discipline with progress bars, plus actual hours and a productivity factor. Instructions tab included.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What are rules of credit?

Rules of credit break each type of work into milestone steps and give each step a weight. Pipe might earn a small share when received, more when erected, the largest share when welded out, and the rest at test and reinstatement. Progress is then the sum of the weights of the steps completed, so it is measured the same way by everyone.

Are the weights in the template a standard?

No. They are common starting points so the workbook shows how it works. Weights are agreed between contractor and owner or EPC for each contract, and changed only by revision.

How is earned % calculated?

For each line item, the template multiplies each step's weight (looked up by discipline from the Rules of Credit tab) by how complete that step is, from 0% to 100%, and adds them up. Earned hours are earned % × the item's budget hours.

What is the productivity factor?

Earned hours divided by actual hours, by discipline. Above 1.00 the crew earned more budget hours than it spent; below 1.00 it spent more than it earned. Enter actual hours from timecards for the same cut-off date.

Who uses rules of credit?

Contractors and owners on industrial, energy and EPC projects where progress drives payment, forecasts and S-curves. Any contractor who wants progress that holds up when the owner walks the job can use the same idea on smaller work.

Can I add disciplines or steps?

Yes. Add rows to the Rules of Credit tab with a discipline name, step number (1 to 6) and weight, then add the discipline to the Progress dropdown or type it in. Keep each discipline's weights at 100%; the check at the top will tell you.

Progress everyone measures the same way

A percent complete that comes from a foreman's gut feel, or from dividing cost by budget, will not hold up when the owner walks the job. Rules of credit fix that: each type of work is split into steps everyone can see, each step carries an agreed weight, and progress is the sum of the steps completed. Receiving material earns a small, agreed slice instead of half the item.

This template is laid out the way EPC and industrial projects usually work: a rules of credit sheet the contractor and owner agree up front, a progress sheet by line item, and a rollup by discipline in earned hours, the one unit that lets you compare concrete, steel and pipe on the same S-curve.

Pair it with the construction work package template to plan the work in packages, and the S-curve template to plot planned vs earned over time. The earned value calculator turns the numbers into CPI and SPI.

In Field PM, crews report quantities and hours by phase code on the daily report, and progress by phase code can be shared live with a connected client from the contractor's own account.