Free EPC turnover template · Excel

Free Mechanical Completion Checklist

Discipline checklists for each system, a tracker that shows which systems are ready for MC, and a certificate to sign it off. For EPC firms, contractors and owners.

  • ✓Piping, equipment, electrical, I&C and civil checks
  • ✓Done / Open / N/A with Cat A or B punch per item
  • ✓% complete by discipline and overall
  • ✓System tracker with progress bars and punch counts
  • ✓Ready for MC, Late and accepted status
  • ✓MC certificate with exceptions and attachments

Mechanical Completion Checklist

We'll email you a copy + send the file to your browser right now.

Excel (.xlsx) · works in Excel, Google Sheets, Numbers

Want it with your logo on it?

A free account puts your logo, company info, and license # on every template, and adds one-click template packs. Free forever, even after the trial.

Get branded templates free →

By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.

What's inside the workbook

Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.

01

MC Checklist

One sheet per system with checks by discipline, punch category, who checked and when, and a three-party sign-off.

02

System MC Tracker

Every system on one page: checks done, % complete bar, open Cat A and B punch, planned and actual MC, and status.

03

MC Certificate

Statement, Cat B exceptions, attachment checklist and signatures, plus an Instructions tab.

Want this automated?

Stop re-typing the same form on every job.

Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.

30 days free · no credit card · every feature unlocked from day one.

Paper / Excel

  • ✗ Hand-writes the form on the jobsite
  • ✗ Re-types into Excel at the trailer
  • ✗ Emails the PDF back to the office
  • ✗ No audit trail, no signatures
  • ✗ Data never feeds payroll or the budget

Field PM

  • ✓ Fill out from a phone in under 3 min
  • ✓ Photos, signatures, and audit log built in
  • ✓ One-click PDF for the GC and owner
  • ✓ Data feeds payroll, budget, and reports
  • ✓ Replaces 5 forms with one platform

On your phone & tablet

Every template — in the app, in your pocket

This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:

Download on theApp StoreGet it onGoogle Play

Frequently asked questions

What is mechanical completion?

Mechanical completion (MC) is the point where a system has been built, installed and tested in line with the drawings and specifications, and is ready for commissioning. It is usually accepted system by system, and the exact definition comes from the contract.

What disciplines does the checklist cover?

Piping, mechanical and equipment, electrical, instrumentation and controls, civil and structural, and documentation. Edit or delete items to match your scope.

What are Category A and B punch items?

A common convention: Category A items must be cleared before mechanical completion is accepted, usually because they affect safety or the ability to commission. Category B items can be finished after MC. Some contracts add Category C. Use your contract's definitions.

How does the System MC Tracker work?

One row per system. Enter the number of checks and how many are done, plus open Cat A and Cat B punch. It calculates % complete with an in-cell progress bar and shows Ready for MC when every check is done and no Cat A punch is open. Late shows when the planned MC date has passed.

What is the difference between mechanical completion and commissioning?

MC proves the system was built right. Commissioning proves it works. Many projects also have a pre-commissioning stage between them. See our commissioning checklist template for the next step.

Is it free?

Yes. Enter your email and the Excel file downloads right away.

Why mechanical completion matters to the owner

For the owner, mechanical completion is the gate between construction and start-up. Accept a system too early and commissioning finds problems that should have been punched. Accept it too late and the start-up schedule slips. A system-by-system tracker gives both sides the same view of what is ready, what is close and what is behind.

This workbook follows the way MC is commonly run on industrial and EPC work: systems defined on the P&IDs, discipline walkdowns, punch split into Category A and B, and a certificate per system. Use it with the A/B/C punch list and the system turnover package.

Field PM runs QA/QC inspections and progress by phase code from the field, and both can be shared live with a connected client. See QA/QC software or, for owners and EPC firms, how Client Connect works.