Free EPC quality template · Excel
Plan every inspection before the work starts: acceptance criteria, references, records, and hold, witness, review and surveillance points for each party.
We'll email you a copy + send the file to your browser right now.
By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.
Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.
01
The plan itself, with a legend, per-party point counts, example piping and concrete activities and a four-party sign-off.
02
Every notification and inspection: notice sent, inspection date, days of notice, who attended, result, release and record number.
03
How to write criteria, the difference between hold and witness, and how to get the ITP approved.
Want this automated?
Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.
30 days free · no credit card · every feature unlocked from day one.
Paper / Excel
Field PM
On your phone & tablet
This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:
The platform behind the templates
An ITP lists every inspection and test for a scope of work in the order it happens, with the acceptance criteria, the document the criteria come from, the record that proves it was done, and who must be involved. It is agreed with the client before the work starts.
H is a hold point: work stops until the named party releases it. W is a witness point: the party is notified and may attend, but work can continue if they do not come at the notified time. R is review of records. S is surveillance, random monitoring without notice. Your contract may define these terms slightly differently, and the contract wins.
Four columns: Contractor, Sub / Vendor, Owner / Client and Third Party (for example an NDE company or authorized inspector). Rename them to match your job. The counts at the top show how many hold, witness and review points each party has.
Yes, piping (material receiving, welding qualification, fit-up, visual, NDE, hydrotest) and concrete (pre-pour, fresh concrete tests, strength results). Replace them with your own scope.
It logs each notification and inspection: when notice went out, when the inspection happened, who attended, the result and who released the hold. The notice column shows how many days of notice you gave, which helps when a hold point is missed and someone asks why.
Yes. Enter your email and the Excel file downloads right away.
On industrial and EPC work, the ITP is where the owner decides how much of the quality work they want to see with their own eyes. Hold points are the owner's guarantee that nothing gets buried or pressurized before it is checked. For the contractor, the ITP sets expectations up front: what will be inspected, by whom, and how much notice is needed. Most hold-point disputes come from an ITP that was never agreed or a notification that was never logged.
This template is built the way ITP matrices are usually laid out on EPC projects, with one column per party so it is clear at a glance where each party intervenes. It works for piping, structural steel, concrete, electrical and instrumentation scopes. Pair it with the NCR template for anything that fails, and the hydrotest test package for pressure testing.
Field PM runs QA/QC inspections from the field with photos and sign-off, and those inspections can be shared live with a connected client. See QA/QC software, or if you manage contractors, see how Client Connect works.