Free Excel template · Cost-plus & GMP
For cost-plus and GMP contracts: cost by code against the GMP line, committed, billed, paid and cost to complete, with fee, contingency, shared savings and an invoice backup register.
We'll email you a copy + send the file to your browser right now.
By downloading you agree to receive occasional Field PM updates. Unsubscribe anytime. We don't share your email — read our privacy policy.
Pre-formatted, print-ready, with embedded Field PM branding. Works in Excel, Google Sheets, and Numbers.
01
Contract inputs and a summary at the top (fee, contingency, projected total, GMP savings split), then one row per cost code with billed and paid pulled from the register.
02
Every vendor invoice and payroll period with cost code, pay application number, paid date and amount, and whether backup is attached.
03
How to set it up from your GMP breakdown, how to record contingency transfers, and what owners look for in an open-book review.
Share this live with your client
On cost-plus and GMP work the owner is paying actual cost plus fee, so they expect to see what was spent, what is committed, and what is left in the GMP.
In Field PM, your invoices, change orders and progress by phase code can be shared live with your client, item by item, from your own account.
Want this automated?
Field PM has this exact form built in — crews fill it out from a phone, the data flows into the project record, and you get a clean PDF for the GC or owner with one click. No re-typing, no lost paperwork, no missed signatures.
30 days free · no credit card · every feature unlocked from day one.
Paper / Excel
Field PM
On your phone & tablet
This template and every other one is built into the Field PM app. Fill them out right from the jobsite on any iPhone, iPad, or Android — photos, signatures, and a clean GC-ready PDF included. Download free:
The platform behind the templates
On a cost-plus or GMP (guaranteed maximum price) contract, the owner pays the contractor's actual cost plus a fee, so the contractor shows its costs openly. The open-book cost report lists cost by code against the budget, what has been billed and paid, what is left to spend, and where the job will land against the GMP.
Enter the fee percentage and the template applies it to cost billed to date and to projected cost. If your contract sets a lump-sum fee or excludes some costs from fee, adjust the two fee formulas to match.
Contingency is its own line. When contingency funds a cost line, enter a negative change on the contingency row and a matching positive change on the line it funds. The summary shows original, used and remaining contingency.
If the projected total of cost plus fee comes in under the GMP, the template splits the difference using the contractor share percentage you enter. Contracts differ on what counts toward savings, so check yours.
Every vendor invoice, payroll period and other cost billed to the owner, with its cost code, the pay application it was billed on, paid date and amount, and whether backup is attached. Cost billed and paid on the cost report roll up from it automatically.
No. It is a management tool for tracking an open-book job. Your contract defines reimbursable cost, fee and savings, and your accountant decides how they are reported.
On a cost-plus or guaranteed maximum price contract, trust depends on the owner being able to follow each billed dollar from the pay application back to an invoice or a payroll report. This template keeps the two halves together: a cost report by code, and a register of every cost behind it.
Contractors use it to send a clean monthly package with the pay application. Owners, program managers and cost consultants use the same layout to review what was billed, how contingency is being spent, and whether the job is heading for savings or an overrun against the GMP.
For lump-sum work, the simpler budget vs actual template or the schedule of values is usually enough. For a full internal forecast, see the job cost report template.
Field PM tracks budgets by phase code with actual labor cost from crew hours, and a contractor can share invoices, change orders and progress by phase code live with a connected client. If you hire contractors across many sites, see how Client Connect works.