AIA G716 in one paragraph
AIA Document G716 — Request for Information is the AIA's standard form for asking the design team to clarify the contract documents. The contractor fills in the question, references the drawings or specifications, proposes a solution if it has one, and sends it through the channel the contract names. The architect answers on the same form. Its value is the paper trail: every question, who asked it, when, what the answer was, and whether it might change cost or time.
What goes on a G716-style RFI
Whether you use the official AIA form or your own, a complete RFI captures the same information. In our own words:
| Part | What to put there | Field tip |
|---|---|---|
| Identification | Project, RFI number, date, who it's from and to | Number RFIs sequentially and never reuse a number |
| Reference | Drawing sheet, detail, spec section, grid/location | Attach a marked-up screenshot of the detail |
| Request | The specific question — one issue per RFI | State the conflict neutrally: "Detail 5/A-501 conflicts with spec 09 21 16" |
| Proposed solution | What you recommend and why | Architects answer a recommendation faster than an open question |
| Impact | Potential cost / schedule impact, response-needed-by date | Flag it even if uncertain — it protects your change-order rights |
| Response | The architect's answer, date, and signature | Log the response date; track days outstanding |
Do you have to use the official G716?
Read your contract's RFI and communications clauses. Many contracts just require written RFIs through a set channel; a contractor-made form with the fields above is normally fine. Some owners or architects require the AIA form or their own portal. If the official document is required, buy it from AIA Contract Documents — it's copyrighted, and "free G716 PDF" downloads are usually unlicensed copies.
What's in the free RFI workbook
- RFI form — number, date, project, priority, drawing/spec reference, question, proposed solution
- Response block — for the architect/engineer, with date and signature
- Impact — cost / schedule impact and "change order required?"
- Sign-off — contractor, design team, owner
- RFI Log tab — a 30-row tracker for every RFI on the job
It's our own layout, built to capture the same information a G716 does — use it wherever a contractor-made RFI is acceptable.
Write RFIs that get answered
- Lead with the recommendation. "Recommend X because Y" gets a yes/no in minutes.
- One question per RFI. A hard question shouldn't hold up an easy one.
- Give a response-needed-by date tied to the schedule.
- Keep the language neutral. Questions get answered; accusations get routed to legal.
For the full walkthrough, see the RFI template guide.
From a spreadsheet to tracked RFIs
A spreadsheet log works until you have forty open RFIs. Field PM's RFI and change order tracking numbers RFIs automatically, tracks ball-in-court and days outstanding, and turns an RFI answer into a change order request in one step. Start a 30-day free trial, no credit card.
Related templates
- RFI Template + Log — the full RFI guide
- Change Order Template — when the RFI answer changes scope
- Pending Change Order Log — track PCO → COR → CO
- Submittal Log
- Document Transmittal