Subcontractor Management for General Contractors: What to Require and How to Track It

Subcontractor management is how a general contractor selects, directs, checks and pays the trade contractors on a job. It works when every sub knows what is required before award and the GC tracks the same few things on every sub, every week.

Published November 25, 2026 · 10 min read

Key takeaway

Require the same things from every sub at each stage: prequalification before award, a daily report while on site, safety and QA/QC records as the work happens, priced change orders with backup, pay apps tied to observed progress, and a complete closeout package. Then carry sub costs and self-perform costs in one job budget so margin is real.

What does subcontractor management cover?

It covers the whole life of a subcontract. Each stage has something to require from the sub and something for the GC to track.

StageRequire from the subGC tracks
PrequalificationLicense, insurance, safety record, references, capacityScore and approval status
AwardSigned subcontract, schedule of values, insurance certificateContract value on the job budget
On siteDaily report with crew, hours, work done, photosManpower and progress against schedule
SafetySite-specific plan, JSAs, toolbox talks, incident reportsHours, incidents and rates
QualityInspections, test reports, punch completionOpen items and repeat failures
ChangesPriced change order requests with backupPending and approved change value
PaymentPay application, lien waivers, current insuranceBilled, paid, retainage held
CloseoutWarranties, as-builts, O&M manuals, final waiverMissing documents by sub

What should you require before awarding a subcontract?

Prequalification is cheaper than replacing a sub mid-job. Ask every bidder for the same package and score it the same way.

ItemWhat to ask forRed flag
LicenseState and local license numbers for the tradeExpired, wrong trade or wrong state
InsuranceCertificate of insurance with your required limits and additional insured wordingLimits below contract, or no additional insured
Safety recordThree years of OSHA 300A summaries, TRIR, DART, EMR letterRates trending up, or no log at all
Safety programWritten program, training records, site-specific plan templateGeneric program with no training records
CapacityCurrent backlog, crew size available for your datesBacklog that cannot absorb your job
Financial strengthBonding capacity or bank referenceCannot bond the job size
ExperienceThree similar jobs with contactsNo work of similar size or type
Quality programQC plan, inspection forms, certificationsNo written inspection process

What should subcontractors report every day?

A sub daily report should answer five questions: who was on site, how many hours, what got installed, what is in the way, and was anyone hurt. If the GC cannot answer those for each sub at the end of the day, the GC is managing from memory.

In Field PM, subcontractor users are free. A GC invites each sub foreman to the project, and the foreman submits a daily report from a phone with crew hours, quantities, delays, safety notes and photos. The report lands in the same project record as the GC's own crews.

How do you track subcontractor safety on a job?

Track subs the way you track your own crews: hours worked, JSAs and toolbox talks completed, observations, and incidents. Job-level rates use the same OSHA formula as company rates, with all contractors' hours and cases on that job.

A sub with a clean company TRIR can still have a bad month on your site. Watch the job numbers, not only the prequalification numbers. See OSHA safety metrics explained for the formulas.

How do you hold subs to a QA/QC standard?

  • •Name the inspection points in the subcontract, including hold points where work cannot continue until the GC or owner signs off.
  • •Use the same inspection forms for every sub in the same trade, so results can be compared.
  • •Log every failed inspection as a nonconformance with a corrective action and a close date.
  • •Track repeat failures by sub. One failure is a mistake. The same failure three times is a process problem.
  • •Close punch items before the sub's final payment, not after.

How should subcontractor change orders flow?

A sub change order request should arrive priced, with labor hours, material quotes and markup shown, and tied to the directive or RFI that caused it. The GC reviews it, adds its own markup, and carries it into the owner change order.

Agree markup rules at award. Disputes over markup percentages are easier to settle in the subcontract than in the middle of a job.

StepWhoWhat to check
RequestSubScope, cause, labor, material, equipment, markup
ReviewGC project managerQuantities, rates, markup against the subcontract terms
Owner change orderGCSub cost plus GC markup, schedule impact
ApprovalOwner, then GC to subSigned change order before the work, or a written directive
BudgetGCApproved value added to the sub's contract line

How do you review a subcontractor pay application?

CheckWhy
Percent complete matches what you saw in the fieldYou pay for work in place, not for time passed
Only approved change orders are billedPending changes are not yet contract value
Retainage is held at the subcontract rateRetainage is your leverage for punch and closeout
Lien waivers for the prior payment are attachedProtects the owner and the GC from liens
Insurance is currentAn expired certificate is uninsured work
Stored materials have backupInvoices, photos and location of stored material

How do self-perform work and subcontracts fit in one job budget?

Many GCs self-perform concrete, carpentry or sitework and subcontract the rest. If self-perform labor lives in one system and subcontracts live in a spreadsheet, nobody sees the real margin until the job is over.

Put both in one budget, by phase code. Self-perform lines collect actual cost from crew hours, materials and equipment. Subcontract lines carry the contract value plus approved change orders, and collect actual cost from sub invoices.

Budget lineBudget comes fromActual cost comes from
Self-perform laborEstimate hours × rateCrew hours from daily reports or time clock × pay rate × burden
Self-perform materialEstimateVendor bills and purchase orders
SubcontractSubcontract value + approved change ordersSub invoices, coded to the phase
General conditionsEstimateSupervision hours, rentals, expenses

How does Field PM handle this today?

In Field PM, a GC records each subcontract on the job with its trade, phase code, contract value, scope and signed documents, and logs sub invoices against the phase code. Those lines sit in the same budget versus actual view as self-performed work. Sub foremen submit daily reports for free.

A GC can also connect to subs that run their own jobs in Field PM and see what each sub shares live, such as daily reports, schedule, change orders and invoices. Feeding a connected sub's progress, quantities and invoices straight into the GC job's subcontract lines is on the roadmap. See subcontractor management software and Field PM for general contractors.

Owners running many sites face the same problem one level up; see how retail chains manage multi-site programs and Field PM for multi-site retail owners. EPC firms with several contractors on one facility can read Field PM for EPC engineering firms.

What should subcontractors deliver at closeout?

  • •Warranties, with start dates and contacts.
  • •As-built drawings or redlines for their scope.
  • •O&M manuals and training records for installed equipment.
  • •Test and inspection reports, including any third-party reports.
  • •Attic stock and spare parts list, if required.
  • •Final lien waiver and consent of surety, if bonded.
  • •Use the free project closeout checklist to track what each sub still owes.

Frequently asked questions

What should a general contractor require from subcontractors?+

Before award: license, insurance with additional insured wording, three years of safety records, capacity and references. On the job: daily reports, safety and QA/QC records, priced change order requests and pay applications with lien waivers. At closeout: warranties, as-builts, O&M manuals and a final lien waiver.

What is subcontractor prequalification?+

Subcontractor prequalification is the review a GC does before a sub can bid or be awarded work. It checks license, insurance, safety record, financial strength, capacity, experience and quality program, usually scored on a weighted sheet.

How do you track subcontractor performance?+

Track the same measures for every sub: manpower against plan, progress against schedule, safety incidents and job-level rates, failed inspections and repeat failures, change order volume, and closeout documents still owed. Review them weekly.

How should a GC review a subcontractor pay application?+

Check that percent complete matches field progress, only approved change orders are billed, retainage is held at the subcontract rate, prior lien waivers are attached, insurance is current and stored materials have backup.

Can self-perform work and subcontracts be tracked in one budget?+

Yes. Budget both by phase code. Self-perform lines take actual cost from crew hours, materials and equipment. Subcontract lines carry contract value plus approved changes and take actual cost from sub invoices. One budget gives one margin for the job.

Do subcontractors have to pay to use Field PM on a GC's project?+

No. Subcontractor users invited to a GC's project in Field PM are free, along with foremen, QA/QC and safety users.

Run the numbers in the field, not the spreadsheet

Field PM turns daily reports into live job costing, productivity, and billing — built for self-perform contractors. 30-day free trial · no credit card · unlimited foremen, QA/QC, safety & subs always free.

Start free trial →

Rated by contractors on

Field PM reviews on CapterraField PM reviews on GetAppField PM reviews on Software Advice