Subcontractor Management for General Contractors: What to Require and How to Track It
Subcontractor management is how a general contractor selects, directs, checks and pays the trade contractors on a job. It works when every sub knows what is required before award and the GC tracks the same few things on every sub, every week.
Published November 25, 2026 · 10 min read
Key takeaway
Require the same things from every sub at each stage: prequalification before award, a daily report while on site, safety and QA/QC records as the work happens, priced change orders with backup, pay apps tied to observed progress, and a complete closeout package. Then carry sub costs and self-perform costs in one job budget so margin is real.
What does subcontractor management cover?
It covers the whole life of a subcontract. Each stage has something to require from the sub and something for the GC to track.
| Stage | Require from the sub | GC tracks |
|---|---|---|
| Prequalification | License, insurance, safety record, references, capacity | Score and approval status |
| Award | Signed subcontract, schedule of values, insurance certificate | Contract value on the job budget |
| On site | Daily report with crew, hours, work done, photos | Manpower and progress against schedule |
| Safety | Site-specific plan, JSAs, toolbox talks, incident reports | Hours, incidents and rates |
| Quality | Inspections, test reports, punch completion | Open items and repeat failures |
| Changes | Priced change order requests with backup | Pending and approved change value |
| Payment | Pay application, lien waivers, current insurance | Billed, paid, retainage held |
| Closeout | Warranties, as-builts, O&M manuals, final waiver | Missing documents by sub |
What should you require before awarding a subcontract?
Prequalification is cheaper than replacing a sub mid-job. Ask every bidder for the same package and score it the same way.
| Item | What to ask for | Red flag |
|---|---|---|
| License | State and local license numbers for the trade | Expired, wrong trade or wrong state |
| Insurance | Certificate of insurance with your required limits and additional insured wording | Limits below contract, or no additional insured |
| Safety record | Three years of OSHA 300A summaries, TRIR, DART, EMR letter | Rates trending up, or no log at all |
| Safety program | Written program, training records, site-specific plan template | Generic program with no training records |
| Capacity | Current backlog, crew size available for your dates | Backlog that cannot absorb your job |
| Financial strength | Bonding capacity or bank reference | Cannot bond the job size |
| Experience | Three similar jobs with contacts | No work of similar size or type |
| Quality program | QC plan, inspection forms, certifications | No written inspection process |
- •Score bidders with the free subcontractor prequalification scorecard.
- •Check safety numbers yourself with the safety incidence rate calculator. Ask for the hours, not just the rate.
- •Track certificate expiry dates with the free certificate of insurance tracker.
What should subcontractors report every day?
A sub daily report should answer five questions: who was on site, how many hours, what got installed, what is in the way, and was anyone hurt. If the GC cannot answer those for each sub at the end of the day, the GC is managing from memory.
In Field PM, subcontractor users are free. A GC invites each sub foreman to the project, and the foreman submits a daily report from a phone with crew hours, quantities, delays, safety notes and photos. The report lands in the same project record as the GC's own crews.
How do you track subcontractor safety on a job?
Track subs the way you track your own crews: hours worked, JSAs and toolbox talks completed, observations, and incidents. Job-level rates use the same OSHA formula as company rates, with all contractors' hours and cases on that job.
A sub with a clean company TRIR can still have a bad month on your site. Watch the job numbers, not only the prequalification numbers. See OSHA safety metrics explained for the formulas.
How do you hold subs to a QA/QC standard?
- •Name the inspection points in the subcontract, including hold points where work cannot continue until the GC or owner signs off.
- •Use the same inspection forms for every sub in the same trade, so results can be compared.
- •Log every failed inspection as a nonconformance with a corrective action and a close date.
- •Track repeat failures by sub. One failure is a mistake. The same failure three times is a process problem.
- •Close punch items before the sub's final payment, not after.
How should subcontractor change orders flow?
A sub change order request should arrive priced, with labor hours, material quotes and markup shown, and tied to the directive or RFI that caused it. The GC reviews it, adds its own markup, and carries it into the owner change order.
Agree markup rules at award. Disputes over markup percentages are easier to settle in the subcontract than in the middle of a job.
| Step | Who | What to check |
|---|---|---|
| Request | Sub | Scope, cause, labor, material, equipment, markup |
| Review | GC project manager | Quantities, rates, markup against the subcontract terms |
| Owner change order | GC | Sub cost plus GC markup, schedule impact |
| Approval | Owner, then GC to sub | Signed change order before the work, or a written directive |
| Budget | GC | Approved value added to the sub's contract line |
- •Work out GC and sub markup on the same change with the change order markup calculator.
How do you review a subcontractor pay application?
| Check | Why |
|---|---|
| Percent complete matches what you saw in the field | You pay for work in place, not for time passed |
| Only approved change orders are billed | Pending changes are not yet contract value |
| Retainage is held at the subcontract rate | Retainage is your leverage for punch and closeout |
| Lien waivers for the prior payment are attached | Protects the owner and the GC from liens |
| Insurance is current | An expired certificate is uninsured work |
| Stored materials have backup | Invoices, photos and location of stored material |
How do self-perform work and subcontracts fit in one job budget?
Many GCs self-perform concrete, carpentry or sitework and subcontract the rest. If self-perform labor lives in one system and subcontracts live in a spreadsheet, nobody sees the real margin until the job is over.
Put both in one budget, by phase code. Self-perform lines collect actual cost from crew hours, materials and equipment. Subcontract lines carry the contract value plus approved change orders, and collect actual cost from sub invoices.
| Budget line | Budget comes from | Actual cost comes from |
|---|---|---|
| Self-perform labor | Estimate hours × rate | Crew hours from daily reports or time clock × pay rate × burden |
| Self-perform material | Estimate | Vendor bills and purchase orders |
| Subcontract | Subcontract value + approved change orders | Sub invoices, coded to the phase |
| General conditions | Estimate | Supervision hours, rentals, expenses |
How does Field PM handle this today?
In Field PM, a GC records each subcontract on the job with its trade, phase code, contract value, scope and signed documents, and logs sub invoices against the phase code. Those lines sit in the same budget versus actual view as self-performed work. Sub foremen submit daily reports for free.
A GC can also connect to subs that run their own jobs in Field PM and see what each sub shares live, such as daily reports, schedule, change orders and invoices. Feeding a connected sub's progress, quantities and invoices straight into the GC job's subcontract lines is on the roadmap. See subcontractor management software and Field PM for general contractors.
Owners running many sites face the same problem one level up; see how retail chains manage multi-site programs and Field PM for multi-site retail owners. EPC firms with several contractors on one facility can read Field PM for EPC engineering firms.
What should subcontractors deliver at closeout?
- •Warranties, with start dates and contacts.
- •As-built drawings or redlines for their scope.
- •O&M manuals and training records for installed equipment.
- •Test and inspection reports, including any third-party reports.
- •Attic stock and spare parts list, if required.
- •Final lien waiver and consent of surety, if bonded.
- •Use the free project closeout checklist to track what each sub still owes.
Frequently asked questions
What should a general contractor require from subcontractors?+
Before award: license, insurance with additional insured wording, three years of safety records, capacity and references. On the job: daily reports, safety and QA/QC records, priced change order requests and pay applications with lien waivers. At closeout: warranties, as-builts, O&M manuals and a final lien waiver.
What is subcontractor prequalification?+
Subcontractor prequalification is the review a GC does before a sub can bid or be awarded work. It checks license, insurance, safety record, financial strength, capacity, experience and quality program, usually scored on a weighted sheet.
How do you track subcontractor performance?+
Track the same measures for every sub: manpower against plan, progress against schedule, safety incidents and job-level rates, failed inspections and repeat failures, change order volume, and closeout documents still owed. Review them weekly.
How should a GC review a subcontractor pay application?+
Check that percent complete matches field progress, only approved change orders are billed, retainage is held at the subcontract rate, prior lien waivers are attached, insurance is current and stored materials have backup.
Can self-perform work and subcontracts be tracked in one budget?+
Yes. Budget both by phase code. Self-perform lines take actual cost from crew hours, materials and equipment. Subcontract lines carry contract value plus approved changes and take actual cost from sub invoices. One budget gives one margin for the job.
Do subcontractors have to pay to use Field PM on a GC's project?+
No. Subcontractor users invited to a GC's project in Field PM are free, along with foremen, QA/QC and safety users.
Run the numbers in the field, not the spreadsheet
Field PM turns daily reports into live job costing, productivity, and billing — built for self-perform contractors. 30-day free trial · no credit card · unlimited foremen, QA/QC, safety & subs always free.
Start free trial →Keep reading