Billing
AIA G702 / G703 Progress Billing Explained (Schedule of Values, Retainage, % Complete)
The AIA G702 and G703 are the standard way contractors bill for work in progress. Once you understand how the Schedule of Values, retainage, and percent-complete math fit together, a pay application becomes a 15-minute job instead of a monthly headache.
Published June 14, 2026 · 8 min read
Key takeaway
The G703 (continuation sheet) is the detail — your Schedule of Values, line by line, showing how much of each item is complete. The G702 (the cover) summarizes it into one number: work completed, less retainage, less prior payments, equals what you are owed this period. Get the SOV right at the start and every pay app after it is arithmetic.
What the G702 and G703 actually are
AIA Document G702, "Application and Certificate for Payment," is the one-page cover sheet of a pay application. It summarizes the contract sum, the work completed to date, retainage withheld, prior payments, and the current amount due — and it carries the contractor's and architect's signatures certifying the request.
AIA Document G703, "Continuation Sheet," is the line-item detail behind that cover. It is your Schedule of Values laid out row by row: each cost item, its scheduled value, how much was completed in prior periods, how much this period, stored materials, the total complete, the percentage, the balance to finish, and retainage on that line.
Together they are the de facto standard for progress billing on commercial work. Owners, GCs, architects, and lenders all expect to see work-in-progress billed this way, which is why understanding the format is worth the effort even if you build your own equivalent.
The Schedule of Values is the foundation
Everything starts with the Schedule of Values (SOV) — the breakdown of your contract sum into billable line items that, added together, equal the total contract. A good SOV balances two competing pressures: enough granularity that you can bill accurately as work progresses, and enough front-loading (within reason and within what the owner will accept) to keep cash flow healthy early.
The SOV becomes the rows of your G703. Once it is set, each billing period you are only answering one question per line: what percentage of this item is now complete?
How the percent-complete math works
For each SOV line, the core calculation is straightforward:
- •Work Completed This Period = (Total % Complete × Scheduled Value) − Work Completed in Prior Periods.
- •Total Completed and Stored = work completed to date + materials stored on site but not yet installed.
- •% Complete (column G on the G703) = Total Completed and Stored ÷ Scheduled Value.
- •Balance to Finish = Scheduled Value − Total Completed and Stored.
Retainage: the money held back
Retainage (or "retention") is a percentage — commonly 5% or 10% — that the owner withholds from each payment as security that you will finish and close out the job. It is calculated on the work completed, accumulates across every pay app, and is released at substantial completion (and final completion for the last portion).
On the G702, retainage reduces what you are paid now: Total Earned Less Retainage = work completed and stored, minus retainage held. Then Current Payment Due = Total Earned Less Retainage − prior certificates (what you have already been paid). Some contracts also allow retainage reduction partway through — for example dropping from 10% to 5% once the job is 50% complete — which your billing needs to handle without re-opening prior periods.
A line-by-line example
Take an SOV line for "Underground conduit" with a scheduled value of $80,000. Last period you billed it at 40% complete ($32,000). This period the work reached 70%.
Total Completed = 70% × $80,000 = $56,000. Work This Period = $56,000 − $32,000 = $24,000. Balance to Finish = $80,000 − $56,000 = $24,000. At 10% retainage, $5,600 is held against this line's $56,000 to date, so the line contributes $50,400 to "earned less retainage." Repeat for every line, total the columns, and the G702 cover writes itself.
Why teams move off spreadsheets
The math is simple; the bookkeeping is not. Carrying prior-period values forward, handling stored materials, applying a retainage change at 50%, keeping change orders in sync with the SOV, and producing a clean PDF the architect will certify — doing all of that by hand in Excel every month is where errors and late billings creep in.
Software that tracks the SOV as a living object solves this: enter this period's percentages (or pull them from field progress), and the G702/G703 PDF, retainage, and balances generate automatically with prior periods already carried. That is how Field PM's AIA progress billing works — your Schedule of Values, change orders, and percent-complete in one place, producing a certified-ready pay application without re-keying.
Frequently asked questions
What is the difference between the AIA G702 and G703?+
The G702 is the one-page "Application and Certificate for Payment" — the summary cover with contract sum, work completed, retainage, prior payments, and amount due, plus signatures. The G703 is the "Continuation Sheet," the line-item detail (your Schedule of Values) showing how much of each item is complete. The G703 rolls up into the totals on the G702.
How is retainage calculated on a pay application?+
Retainage is a set percentage (commonly 5% or 10%) withheld from the value of work completed as security. It is calculated on completed work each period, accumulates across pay apps, and is released at substantial and final completion. On the G702 it reduces the current amount due via the "Total Earned Less Retainage" line.
What is a Schedule of Values?+
The Schedule of Values (SOV) breaks your total contract sum into billable line items that sum back to the contract total. It defines the rows of the G703 continuation sheet, and each billing period you update the percent complete on each line to generate that period's pay application.
How do you calculate percent complete for billing?+
For each SOV line, % Complete = (Work Completed to Date + Stored Materials) ÷ Scheduled Value. Work billed this period equals total completed-to-date minus what was billed in prior periods, so you never double-bill an item across periods.
Can I bill for stored materials I have not installed yet?+
Often yes, if the contract allows it. Stored materials delivered to the site (or a bonded warehouse) but not yet installed get their own column on the G703 and count toward total completed-and-stored, subject to documentation requirements like invoices and proof of insurance.
Run the numbers in the field, not the spreadsheet
Field PM turns daily reports into live job costing, productivity, and billing — built for self-perform contractors. 30-day free trial · no credit card · unlimited foremen, QA/QC, safety & subs always free.
Start free trial →