Project Management

The Construction Submittal Process, Step by Step

Submittals rarely make headlines on a job, which is exactly why they cause so much quiet damage. A submittal that goes in two weeks late, or comes back stamped revise and resubmit, can push a material delivery past the date the crew needs it, and nobody connects the dots until the work is stalled. Managing submittals well is mostly about starting early and tracking relentlessly. Here is how the process works and where it goes wrong.

Published June 29, 2026 · 7 min read

Key takeaway

Submittals prove the products and fabrication match the design before anything is ordered or built. They flow from sub to GC to architect or engineer and back, and the schedule risk lives in the lead time, so track every submittal on a log and process long-lead items first.

What submittals actually are

A submittal is the contractor's documentation that the materials, equipment, and fabrication they intend to provide conform to the contract documents. It is the design team's chance to confirm what you plan to install matches what they specified, before money is committed and steel is cut.

They come in a few forms, and the type drives how much review time to expect.

  • Shop drawings: detailed fabrication and installation drawings, common for steel, rebar, millwork, and MEP
  • Product data: manufacturer cut sheets, specifications, and performance data for specified products
  • Samples: physical examples of finishes, colors, and materials for the design team to approve
  • Other: mock-ups, certificates, calculations, and warranties called out in the specs

The review workflow

Submittals move along a predictable path, and a delay at any handoff pushes the whole chain. Knowing each step lets you see where a package is stuck and who is holding it.

  • The subcontractor or supplier prepares the submittal per the specification
  • The GC reviews it for completeness and coordination, then forwards or returns it
  • The architect or engineer reviews against the design and applies a review stamp
  • The stamped submittal comes back down the chain to the sub or supplier
  • Once approved or approved as noted, the material can be ordered or fabrication can start

Approval stamps and what they mean

The review stamp tells you whether you can proceed, and reading it correctly prevents costly missteps. Exact wording varies by reviewer, but the categories are consistent.

Approved or no exceptions taken means proceed. Approved as noted or make corrections noted means proceed while incorporating the marked changes, usually without resubmitting. Revise and resubmit means the package is not acceptable and must be corrected and run through the full cycle again, which is the one that hurts your schedule because it restarts the clock. Rejected means start over. A review stamp generally does not relieve you of responsibility for accuracy or for meeting the contract, so do not treat an approval as a transfer of liability.

Why the submittal log is non-negotiable

A submittal log, or register, lists every required submittal with its spec section, who is responsible, the dates it moved through each step, its current status, and the required-by date. Without it, packages slip silently and you find out only when the field is waiting on material that was never ordered because the submittal was never approved.

The log is also your early-warning system. Sorted by required-by date, it tells you which submittals must move now to protect the schedule. Keeping the submittal log alongside your daily reports and look-ahead schedule in Field PM means the same information that drives the field also flags a stalled submittal before it becomes a stalled crew.

Lead time is where submittals wreck schedules

The real schedule risk is not the review itself but the total lead time: preparation, review cycles, and then fabrication and delivery after approval. For a long-lead item like switchgear, structural steel, elevators, or custom glazing, that total can run months, and the clock does not start until the submittal is approved.

Work backward from the date the field needs the material. Subtract fabrication and delivery time, subtract the review cycle plus a buffer for one revise-and-resubmit, and that is your deadline to get the submittal in. Identify long-lead items at the start of the job and process those submittals first, before the easy ones, because they are the ones that will stop the job if they slip. A single late switchgear submittal can idle an entire electrical crew weeks later, long after anyone remembers the paperwork was the cause.

Frequently asked questions

What is the difference between shop drawings and product data?+

Shop drawings are detailed fabrication and installation drawings the contractor or supplier produces for items like structural steel, rebar, and millwork. Product data is manufacturer-provided information, such as cut sheets and performance specs, for products being supplied as specified. Shop drawings typically require more review time because they are project-specific.

What does revise and resubmit mean on a submittal?+

It means the submittal is not acceptable as is and must be corrected and run through the full review cycle again. It is the stamp that most damages your schedule because it restarts the review clock. Catching errors before submitting, and proposing a clean package the first time, is how you avoid it.

Why are long-lead items so important to submit early?+

Long-lead items like switchgear, structural steel, elevators, and custom glazing can take months to fabricate and deliver, and that clock does not start until the submittal is approved. Submitting them first protects the schedule, because a late approval on a long-lead item can idle a crew weeks down the line.

Does an approved submittal mean I am off the hook for errors?+

Generally no. A review stamp confirms the submittal appears to conform to the design intent, but it usually does not relieve the contractor of responsibility for accuracy, dimensions, quantities, or compliance with the contract documents. Read your contract's submittal clause, because it spells out exactly what an approval does and does not transfer.

Run the numbers in the field, not the spreadsheet

Field PM turns daily reports into live job costing, productivity, and billing — built for self-perform contractors. 30-day free trial · no credit card · unlimited foremen, QA/QC, safety & subs always free.

Start free trial →